Solar, wind and battery projects near Abingdon (OX14)
48 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OX14 (Vale of White Horse): 5 are waiting for a planning decision, 26 approved but not yet running, 8 operational. The largest live scheme is Culham Science Centre, Clifton Hampden (500 MW battery storage, approved on 22 July 2025, not yet built), 3.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of OX14
Projects of 1 MW and more (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Appleford Sidings, Sutton Courtenaysolar farm | solar farm | 24 | application submitted may be out of dateupdated Jun 2021 | May 2021 | — | Jun 2021 | Vale of White Horse | 3.2 |
| Culham Science Centre, Clifton Hampdenbattery storage | battery storage | 500 | approved, not builtupdated Aug 2025 | May 2024 | granted Jul 2025 | Aug 2025 | South Oxfordshire | 3.2 |
| Culham Science Centrebattery storage | battery storage | 250 | abandonedupdated Jun 2020 | Jul 2016 | — | Jun 2020 | South Oxfordshire | 3.5 |
| Land adjacent to Culham Science Centresolar farm | solar farm | 7 | abandonedupdated Jan 2017 | Nov 2014 | granted Nov 2015 | Jan 2017 | South Oxfordshire | 3.7 |
| Radley College, Kennington Gate Solar Array & Battery Storagesolar farm | solar farm | 2 | approved, not builtupdated May 2024 | Apr 2023 | granted Aug 2023 | May 2024 | Vale of White Horse | 3.8 |
| Applefordbattery storage | battery storage | 300 | approved, not builtupdated Feb 2026 | Jan 2025 | granted Aug 2025 | Feb 2026 | Vale of White Horse | 4.6 |
| Nuneham Courtenay Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Jun 2024 | Apr 2024 | — | Jun 2024 | South Oxfordshire | 5.3 |
| Burcot Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Dec 2023 | refused Feb 2024 | Feb 2026 | South Oxfordshire | 5.9 |
| Burcot Solar Farmbattery storage | battery storage | 49.9 | approved, not builtupdated Feb 2026 | Dec 2023 | refused Feb 2024 | Feb 2026 | South Oxfordshire | 5.9 |
| Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Jan 2024 | Nov 2020 | granted Jan 2022 | Jan 2024 | South Oxfordshire | 6.4 |
| Goose Willow Farm - extensionsolar farm | solar farm | 7 | operationalupdated Jul 2016 | Sep 2013 | granted Dec 2013 | Jul 2016 | Vale of White Horse | 6.4 |
| Goose Willow Farmsolar farm | solar farm | 11.5 | operationalupdated Feb 2014 | Oct 2012 | granted Dec 2012 | Feb 2014 | Vale of White Horse | 6.6 |
| Burcot Farm Battery Storagebattery storage | battery storage | 49.9 | application withdrawnupdated Nov 2023 | Jun 2023 | — | Nov 2023 | South Oxfordshire | 6.7 |
| Steventon Solar Parksolar farm | solar farm | 10 | operationalupdated Sep 2018 | Jul 2012 | granted Oct 2012 | Sep 2018 | Vale of White Horse | 7.0 |
| Landmead Farm (East Hanney)solar farm | solar farm | 46 | operationalupdated Feb 2017 | Jul 2013 | granted Oct 2013 | Feb 2017 | Vale of White Horse | 7.2 |
| Hill Farm Solar Park (VoWH)solar farm | solar farm | 14.8 | operationalupdated Apr 2014 | Jul 2013 | granted Oct 2013 | Apr 2014 | Vale of White Horse | 7.6 |
| Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage | battery storage | 200 | approved, not builtupdated Oct 2025 | Oct 2024 | granted Jul 2025 | Oct 2025 | South Oxfordshire | 7.6 |
| Reading Roadsolar farm | solar farm | 25 | application withdrawnupdated Jul 2014 | Apr 2014 | — | Jul 2014 | Vale of White Horse | 7.8 |
| Wally Corner Landfill Sitesolar farm | solar farm | 7 | operationalupdated Nov 2016 | Jul 2015 | granted Sep 2015 | Nov 2016 | South Oxfordshire | 8.0 |
| Cowley electricity sub-stationbattery storage | battery storage | 49.9 | operationalupdated Mar 2026 | Feb 2019 | granted Jun 2019 | Mar 2026 | Oxford | 8.3 |
| Lower road, Garsingtonbattery storage | battery storage | 100 | refusedupdated Oct 2025 | Nov 2024 | refused Aug 2025 | Oct 2025 | South Oxfordshire | 8.7 |
| Barnstaples Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Oct 2024 | Dec 2021 | granted Feb 2024 | Oct 2024 | Vale of White Horse | 8.7 |
| Chadwicks Farmsolar farm | solar farm | 20 | refused on appealupdated Aug 2015 | Jan 2015 | refused Apr 2015 | Aug 2015 | Vale of White Horse | 9.0 |
| BMW UK Manufacturing Ltdrooftop solar | rooftop solar | 3 | operationalupdated Dec 2014 | — | — | Dec 2014 | Oxford | 9.1 |
| Botleysolar farm | solar farm | 50 | refusedupdated Mar 2026 | Dec 2024 | refused Nov 2025 | Mar 2026 | Vale of White Horse | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Blacklands Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 | Vale of White Horse | 1.9 |
| Building One, Wyndyke Furlongrooftop solar | rooftop solar | 0.2 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Vale of White Horse | 1.9 |
| Building B1, Culham Science Centre, Clifton Hampdenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | South Oxfordshire | 3.1 |
| Appleford Sidings, Sutton Courtenaybattery storage | battery storage | — | application submitted may be out of dateupdated Jun 2021 | May 2021 | — | Jun 2021 | Vale of White Horse | 3.2 |
| Culham Science Centre, Building E4, E5 & E6, Clifton Hampdenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | South Oxfordshire | 3.4 |
| Building M1, Culham Science Centre, Clifton Hampdenrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Aug 2022 | Jul 2022 | South Oxfordshire | 3.5 |
| Radley College, Kennington Gate Solar Array & Battery Storagebattery storage | battery storage | — | approved, not builtupdated May 2024 | Apr 2023 | granted Aug 2023 | May 2024 | Vale of White Horse | 3.8 |
| The Sutton Courtenay Waste Management Site, Appleford Sidingsbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Jun 2025 | granted Jul 2025 | Feb 2026 | Vale of White Horse | 4.0 |
| Milton Park, Miltonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2025 | Feb 2025 | granted Mar 2025 | Jun 2025 | Vale of White Horse | 4.9 |
| Brook Drive, Milton Parkrooftop solar | rooftop solar | — | approved, not builtupdated Jul 2025 | May 2025 | granted Jun 2025 | Jul 2025 | Vale of White Horse | 4.9 |
| Sandford Lane, Kenningtonbattery storage | battery storage | — | application withdrawnupdated May 2026 | Aug 2025 | — | May 2026 | Vale of White Horse | 4.9 |
| Hachette UK Distribution Centre, Milton Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Mar 2026 | Sep 2024 | granted Nov 2024 | Mar 2026 | Vale of White Horse | 5.3 |
| Rebellion Film Studios, Milton Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Feb 2023 | Nov 2022 | granted Jan 2023 | Feb 2023 | Vale of White Horse | 5.4 |
| Littlemore Mental Health Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2026 | Dec 2025 | granted Jan 2026 | Feb 2026 | Oxford | 6.3 |
| Nuneham Courtenay Solar Farm & Battery Storage Facilitybattery storage | battery storage | — | approved, not built may be out of dateupdated Jan 2024 | Nov 2020 | granted Jan 2022 | Jan 2024 | South Oxfordshire | 6.4 |
| Sainsburys Supermarkets, Central Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | South Oxfordshire | 7.2 |
| Millets Farm Centre, Kingston Roadsolar farm | solar farm | 0.8 | approved, not built may be out of dateupdated Feb 2023 | Sep 2022 | granted Jan 2023 | Feb 2023 | Vale of White Horse | 7.3 |
| Verge By Abingdon Road, Broadwaybattery storage | battery storage | 0.2 | refusedupdated May 2026 | Jun 2025 | refused Feb 2026 | May 2026 | South Oxfordshire | 7.5 |
| David Lloyd Leisure, John Smith Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Oxford | 8.5 |
| Oxford Biomedica, Alec Issigonis Wayrooftop solar | rooftop solar | — | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Oxford | 8.7 |
| Barnstaples Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2024 | Apr 2020 | granted Feb 2024 | Oct 2024 | Vale of White Horse | 8.7 |
| Riverside House, Osney Meadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Oxford | 8.9 |
| The Oxford Spires Academy, Glanville Roadrooftop solar | rooftop solar | 0.5 | application submittedupdated Apr 2024 | Aug 2024 | — | Apr 2024 | Oxford | 9.1 |
Distance from the average position of the OX14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 17 | 2 | 5 | 6 | 2 | 226 |
| Rooftop solar | 16 | 2 | 13 | 1 | 0 | 4.7 |
| Battery storage | 15 | 1 | 8 | 1 | 2 | 1,050 |
MW in pipeline: pending, approved and under-construction capacity.
How Vale of White Horse decides solar, wind and battery applications
| Applications | Vale of White Horse | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 31 | 10,236 |
| Refused | 5 (16%) | 19% |
| Solar refused | 5 of 25 | 12% |
| Onshore wind refused | 0 of 1 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
All projects in Vale of White Horse
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near OX14, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.