Energy Projects Near You

Wally Corner Landfill Site (7 MW solar farm)

Wally Corner Landfill Site is a 7 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 23 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
23 November 2016record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
22 July 2015Application submitted
29 September 2015Planning permission granted
15 October 2016Construction started
15 March 2017Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
23 November 2016
Operator or applicant
SBC Renewables
Planning authority
South Oxfordshire
Planning application reference
P15/S2486/FUL
Site area
13.0 ha
Address (REPD)
Land off, Burcot Lane, Dorchester-on-Thames, Berinsfield, Wallingford
Council area (by location)
South Oxfordshire
Time to decision
10 weeks
REPD reference
5551

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Burcot Farm Battery Storagebattery storage49.9application withdrawn1.3
Burcot Solar Farmsolar farm49.9approved, not built2.3
Culham Science Centrebattery storage250abandoned4.6
Land adjacent to Culham Science Centresolar farm7abandoned4.7
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built4.8
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built5.2
Nuneham Courtenay Solar Farmsolar farm49.9application submitted5.6
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built5.7
Lower road, Garsingtonbattery storage100refused6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6574, -1.1619).