Lower road, Garsington (100 MW battery storage)

Lower road, Garsington is a 100 MW battery storage project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 13 August 2025; the record was last updated on 7 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
refusedstatus in REPD
7 October 2025record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
15 November 2024Application submitted
13 August 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
refused
Record last updated
7 October 2025
Operator or applicant
Net Zero Twenty One Ltd
Planning authority
South Oxfordshire
Planning application reference
P24/S3557/FUL
Address (REPD)
Lower Road, Garsington, Oxford
Council area (by location)
South Oxfordshire
Time to decision
39 weeks
Name in REPD
Lower road, Garsington - Energy Storage System
REPD reference
17752

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Cowley electricity sub-stationbattery storage49.9operational1.2
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built1.2
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built2.4
Nuneham Courtenay Solar Farmsolar farm49.9application submitted3.4
Burcot Solar Farmsolar farm49.9approved, not built5.3
Burcot Farm Battery Storagebattery storage49.9application withdrawn6.0
Wally Corner Landfill Sitesolar farm7operational6.1
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built6.8
Culham Science Centrebattery storage250abandoned7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7119, -1.1712).