Energy Projects Near You

Burcot Solar Farm (49.9 MW)

Burcot Solar Farm is a 49.9 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 March 2025, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
4 December 2023Application submitted
28 February 2024Refused by the planning authority
4 March 2025Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Ethical Power
Planning authority
South Oxfordshire
Planning application reference
P23/S4132/FUL
Site area
88.1 ha
Address (REPD)
Burcot Farm Burcot
Council area (by location)
South Oxfordshire
Time to decision
12 weeks
Contracts for Difference
AR7a
REPD reference
15443

The scheme also includes 49.9 MW of battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Burcot Solar Farm P22/S0960/FUL49.910 March 2022refused 6 December 2022

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Burcot Farm Battery Storagebattery storage49.9application withdrawn1.1
Wally Corner Landfill Sitesolar farm7operational2.3
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built2.7
Culham Science Centrebattery storage250abandoned2.8
Land adjacent to Culham Science Centresolar farm7abandoned3.1
Nuneham Courtenay Solar Farmsolar farm49.9application submitted3.6
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built4.0
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built4.1
Applefordbattery storage300approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6663, -1.1912).