Energy Projects Near You

Land adjacent to Culham Science Centre (7 MW solar farm)

Land adjacent to Culham Science Centre is a 7 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 24 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
abandonedstatus in REPD
24 January 2017record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
11 November 2014Application submitted
18 November 2015Planning permission granted
18 November 2018Permission expired

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
abandoned
Record last updated
24 January 2017
Operator or applicant
Culham Renewables
Planning authority
South Oxfordshire
Planning application reference
P14/S3192/FUL
Site area
7.3 ha
Address (REPD)
Fullamoor Farm House, Clifton Hampden, Abingdon
Council area (by location)
South Oxfordshire
Time to decision
53 weeks
REPD reference
4749

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Culham Science Centrebattery storage250abandoned0.6
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built1.2
Applefordbattery storage300approved, not built2.4
Burcot Solar Farmsolar farm49.9approved, not built3.1
Burcot Farm Battery Storagebattery storage49.9application withdrawn3.5
Appleford Sidings, Sutton Courtenaysolar farm24application submitted3.5
Wally Corner Landfill Sitesolar farm7operational4.7
Nuneham Courtenay Solar Farmsolar farm49.9application submitted5.0
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6521, -1.2301).