Appleford (300 MW battery storage)

Appleford is a 300 MW battery storage project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 August 2025, not yet built; the record was last updated on 10 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

300 MWbattery storage
approved, not builtstatus in REPD
10 February 2026record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
29 January 2025Application submitted
8 August 2025Planning permission granted
8 August 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
300 MW
Status (REPD)
approved, not built
Record last updated
10 February 2026
Operator or applicant
TBC 001 Limited
Planning authority
Vale of White Horse
Planning application reference
P25/V0149/FUL
Address (REPD)
S/O B4016 Appleford
Council area (by location)
Vale of White Horse
Time to decision
27 weeks
Name in REPD
Appleford - Battery Energy Storage
REPD reference
17837

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land adjacent to Culham Science Centresolar farm7abandoned2.4
Appleford Sidings, Sutton Courtenaysolar farm24application submitted2.5
Culham Science Centrebattery storage250abandoned3.0
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built3.6
Burcot Farm Battery Storagebattery storage49.9application withdrawn5.2
Burcot Solar Farmsolar farm49.9approved, not built5.2
Wally Corner Landfill Sitesolar farm7operational6.3
Reading Roadsolar farm25application withdrawn6.9
Goose Willow Farm - extensionsolar farm7operational7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6323, -1.243).