Burcot Farm Battery Storage (49.9 MW)

Burcot Farm Battery Storage is a 49.9 MW battery storage project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 3 November 2023; the record was last updated on 24 November 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
application withdrawnstatus in REPD
24 November 2023record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
23 June 2023Application submitted
3 November 2023Application withdrawn

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
application withdrawn
Record last updated
24 November 2023
Operator or applicant
Burcot Solar Farm Limited
Planning authority
South Oxfordshire
Planning application reference
P23/S2095/FUL
Address (REPD)
Burcot Farm Burcot
Council area (by location)
South Oxfordshire
REPD reference
14303

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Burcot Solar Farmsolar farm49.9approved, not built1.1
Wally Corner Landfill Sitesolar farm7operational1.3
Culham Science Centrebattery storage250abandoned3.3
Land adjacent to Culham Science Centresolar farm7abandoned3.5
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built3.5
Nuneham Courtenay Solar Farmsolar farm49.9application submitted4.7
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built4.9
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built5.0
Applefordbattery storage300approved, not built5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6586, -1.1811).