Energy Projects Near You

Nuneham Courtenay Solar Farm (49.9 MW)

Nuneham Courtenay Solar Farm is a 49.9 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 April 2024, no decision recorded; the record was last updated on 3 June 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
3 June 2024record last updated
South Oxfordshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
22 April 2024Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
3 June 2024
Operator or applicant
RES Limited
Planning authority
South Oxfordshire
Planning application reference
P24/S1336/FUL
Site area
56.9 ha
Address (REPD)
Nw/O A4074 Nuneham Courtenay, Oxford,
Council area (by location)
South Oxfordshire
Name in REPD
Nuneham Courtenay - Solar Farm
REPD reference
12387

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built1.0
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built2.4
Cowley electricity sub-stationbattery storage49.9operational3.1
Lower road, Garsingtonbattery storage100refused3.4
Burcot Solar Farmsolar farm49.9approved, not built3.6
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built3.8
Culham Science Centrebattery storage250abandoned4.4
Burcot Farm Battery Storagebattery storage49.9application withdrawn4.7
Land adjacent to Culham Science Centresolar farm7abandoned5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.696, -1.2132).