Nuneham Courtenay Solar Farm & Battery Storage Facility (49.9 MW)

Nuneham Courtenay Solar Farm & Battery Storage Facility is a 49.9 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 January 2022, not yet built; the record was last updated on 19 January 2024. REPD records the planning permission as expiring on 11 January 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
19 January 2024record last updated
South Oxfordshirecouncil area

REPD records the planning permission as expiring on 11 January 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
16 November 2020Application submitted
11 January 2022Planning permission granted
11 January 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
19 January 2024
Operator or applicant
Enso Energy (Cowley Baldon Green Limited)
Planning authority
South Oxfordshire
Planning application reference
P20/S4360/FUL
Site area
139.0 ha
Address (REPD)
Land South West of Cowley Subs, Nuneham Courtenay, Oxford,
Council area (by location)
South Oxfordshire
Time to decision
60 weeks
Contracts for Difference
AR5
REPD reference
7936

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Nuneham Courtenay Solar Farmsolar farm49.9application submitted1.0
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built1.5
Cowley electricity sub-stationbattery storage49.9operational2.0
Lower road, Garsingtonbattery storage100refused2.4
Burcot Solar Farmsolar farm49.9approved, not built4.0
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built4.7
Burcot Farm Battery Storagebattery storage49.9application withdrawn5.0
Culham Science Centrebattery storage250abandoned5.3
Wally Corner Landfill Sitesolar farm7operational5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7021, -1.2018).