Energy Projects Near You

Cowley electricity sub-station (49.9 MW battery storage)

Cowley electricity sub-station is a 49.9 MW battery storage project in Oxford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 June 2021; the record was last updated on 9 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
operationalstatus in REPD
9 March 2026record last updated
Oxfordcouncil area

Planning timeline

DateStage
25 February 2019Application submitted
4 June 2019Planning permission granted
15 November 2019Construction started
22 June 2021Operational

Project details

Technology
battery storage (co-located with fossil fuel plant)
Capacity
49.9 MW
Status (REPD)
operational
Record last updated
9 March 2026
Operator or applicant
Pivot Power
Planning authority
South Oxfordshire
Planning application reference
P19/S0623/FUL
Address (REPD)
Cowley Main Sub Station, Lower Blackberry Lane, Garsington, Oxford
Council area (by location)
Oxford
Time to decision
14 weeks
REPD reference
7571

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower road, Garsingtonbattery storage100refused1.2
Cowley Substation, Blackberry Lane Battery Storage Energy Systembattery storage200approved, not built1.7
Nuneham Courtenay Solar Farm & Battery Storage Facilitysolar farm49.9approved, not built2.0
Nuneham Courtenay Solar Farmsolar farm49.9application submitted3.1
Burcot Solar Farmsolar farm49.9approved, not built5.7
Burcot Farm Battery Storagebattery storage49.9application withdrawn6.6
Culham Science Centre, Clifton Hampdenbattery storage500approved, not built6.8
Wally Corner Landfill Sitesolar farm7operational6.9
Culham Science Centrebattery storage250abandoned7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7176, -1.186).