Goose Willow Farm (11.5 MW solar farm)

Goose Willow Farm is an 11.5 MW solar farm project in Vale of White Horse, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 December 2013; the record was last updated on 28 February 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWsolar farm
operationalstatus in REPD
28 February 2014record last updated
Vale of White Horsecouncil area

Planning timeline

DateStage
18 October 2012Application submitted
11 December 2012Planning permission granted
31 July 2013Construction started
23 December 2013Operational

Project details

Technology
solar farm
Capacity
11.5 MW
Status (REPD)
operational
Record last updated
28 February 2014
Operator or applicant
IKAROS SOLAR LIMITED
Planning authority
Vale of White Horse
Planning application reference
P12/V2112/FUL
Site area
25.8 ha
Address (REPD)
Hanney Road, Abingdon, Oxfordshire
Council area (by location)
Vale of White Horse
Time to decision
8 weeks
REPD reference
1716

Who decides

ApplicationsVale of White HorseUK
Decided applications (solar, wind, battery)3110,236
Refused5 (16%)19%
Solar refused5 of 2512%
Onshore wind refused0 of 145%
Battery storage refused0 of 516%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Steventon Solar Parksolar farm10operational0.4
Goose Willow Farm - extensionsolar farm7operational0.6
Landmead Farm (East Hanney)solar farm46operational1.5
Hill Farm Solar Park (VoWH)solar farm14.8operational2.2
Barnstaples Farmsolar farm49.9approved, not built3.0
Reading Roadsolar farm25application withdrawn3.4
Chadwicks Farmsolar farm20refused on appeal3.7
Elms Farmsolar farm29operational4.6
Appleford Sidings, Sutton Courtenaysolar farm24application submitted5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6359, -1.3569).