The Flit (10.5 MW solar farm)

The Flit is a 10.5 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.5 MWsolar farm
operationalstatus in REPD
4 October 2016record last updated
Cherwellcouncil area

Planning timeline

DateStage
20 May 2014Application submitted
7 August 2014Planning permission granted
1 December 2014Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
10.5 MW
Status (REPD)
operational
Record last updated
4 October 2016
Operator or applicant
United Photovoltaics
Planning authority
Cherwell
Planning application reference
14/00786/F
Site area
18.2 ha
Address (REPD)
Land Parcel 9827, South East Of Yarnton And North Of Woodstock Road, Yarnton, Oxfordshire
Council area (by location)
Cherwell
Time to decision
11 weeks
REPD reference
2071

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Minnis Farmsolar farm5permission expired0.3
Woodstock Road, Yarntonbattery storage52approved, not built0.4
Botley West Solar Projectsolar farm840application submitted3.9
Botleysolar farm50refused5.5
Manor Farm, Noke Solar Farmsolar farm45approved, not built6.0
Rowles Farm solar parksolar farm13operational6.4
Blenheim Net Zero Estatesolar farm5under construction6.6
Wadley Hill Farmsolar farm5refused7.1
Aurora Solar Farmsolar farm32under construction8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8046, -1.294).