Manor Farm, Noke Solar Farm (45 MW)

Manor Farm, Noke Solar Farm is a 45 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 September 2025, not yet built; the record was last updated on 30 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45 MWsolar farm
approved, not builtstatus in REPD
30 September 2025record last updated
Cherwellcouncil area

Planning timeline

DateStage
7 June 2022Application submitted
18 July 2024Refused by the planning authority
16 September 2025Planning permission granted
16 September 2025Appeal allowed
16 September 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
45 MW
Status (REPD)
approved, not built
Record last updated
30 September 2025
Operator or applicant
Green Nation
Planning authority
Cherwell
Planning application reference
22/01682/F
Site area
43.8 ha
Address (REPD)
Manor Farm, Noke, Oxford
Council area (by location)
Cherwell
Time to decision
171 weeks
Name in REPD
Manor Farm, Noke - Solar Farm
REPD reference
11556

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rowles Farm solar parksolar farm13operational2.5
Wadley Hill Farmsolar farm5refused4.3
New Stone Housesolar farm12.5operational5.4
The Flitsolar farm10.5operational6.0
Minnis Farmsolar farm5permission expired6.3
Woodstock Road, Yarntonbattery storage52approved, not built6.4
Brooks Farm Solar Parksolar farm8operational6.5
Home Farm (Merton solar)solar farm18.3operational6.6
Ray Valley Solar Farmsolar farm19under construction6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8229, -1.212).