Energy Projects Near You

Brooks Farm Solar Park (8 MW)

Brooks Farm Solar Park is an 8 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 March 2015; the record was last updated on 1 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8 MWsolar farm
operationalstatus in REPD
1 April 2015record last updated
Cherwellcouncil area

Planning timeline

DateStage
13 June 2014Application submitted
5 September 2014Planning permission granted
1 January 2015Construction started
28 March 2015Operational

Project details

Technology
solar farm
Capacity
8 MW
Status (REPD)
operational
Record last updated
1 April 2015
Operator or applicant
Green Energy UK Direct Ltd
Planning authority
Cherwell
Planning application reference
14/00950/F
Site area
14.2 ha
Address (REPD)
Brooks Farm Murcott Road Lower Arncott
Council area (by location)
Cherwell
Time to decision
12 weeks
REPD reference
2307

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ray Valley Solar Farmsolar farm19under construction0.4
Home Farm (Merton solar)solar farm18.3operational1.5
New Stone Housesolar farm12.5operational3.8
Manor Farm, Noke Solar Farmsolar farm45approved, not built6.5
Rowles Farm solar parksolar farm13operational6.5
Bicester Road, Launtonbattery storage40approved, not built6.9
Pool Farm, Mill Lane, Stratton Solar Farmsolar farm44approved, not built8.6
Wadley Hill Farmsolar farm5refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8539, -1.1318).