Solar, wind and battery projects near Bicester (OX26)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OX26 (Cherwell): 4 are waiting for a planning decision, 17 approved but not yet running, 5 operational. The largest live scheme is Manor Farm, Noke Solar Farm (45 MW solar farm, approved on 16 September 2025, not yet built), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of OX26
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Home Farm (Merton solar)solar farm | solar farm | 18.3 | operationalupdated Nov 2013 | Oct 2012 | granted Feb 2013 | Nov 2013 | Cherwell | 4.1 |
| New Stone Housesolar farm | solar farm | 12.5 | operationalupdated Apr 2015 | Apr 2014 | granted Jul 2014 | Apr 2015 | Cherwell | 4.1 |
| Pool Farm, Mill Lane, Stratton Solar Farmsolar farm | solar farm | 44 | approved, not builtupdated Jun 2025 | Jan 2023 | granted May 2025 | Jun 2025 | Cherwell | 4.3 |
| Bicester Road, Launtonbattery storage | battery storage | 40 | approved, not builtupdated Sep 2024 | Apr 2024 | granted Sep 2024 | Sep 2024 | Cherwell | 4.5 |
| Station Road, Ardley Solar Farm & Battery Energy Storage Systemsolar farm | solar farm | 10.5 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 | Cherwell | 5.3 |
| Station Road, Ardley Solar Farm & Battery Energy Storage Systembattery storage | battery storage | 4 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 | Cherwell | 5.3 |
| Brooks Farm Solar Parksolar farm | solar farm | 8 | operationalupdated Apr 2015 | Jun 2014 | granted Sep 2014 | Apr 2015 | Cherwell | 5.5 |
| Ray Valley Solar Farmsolar farm | solar farm | 19 | under constructionupdated Jun 2023 | Feb 2020 | granted Dec 2020 | Jun 2023 | Cherwell | 5.8 |
| Rowles Farm solar parksolar farm | solar farm | 13 | operationalupdated Oct 2016 | Jul 2013 | granted Apr 2014 | Oct 2016 | Cherwell | 8.0 |
| Fewcott Wind Farmwind farm | wind farm | 9.2 | abandonedupdated Jul 2015 | Dec 2008 | granted Jul 2010 | Jul 2015 | Cherwell | 8.3 |
| Shelswell Park Solar Farmsolar farm | solar farm | 5 | operationalupdated Feb 2014 | Feb 2011 | granted May 2011 | Feb 2014 | Cherwell | 8.5 |
| Manor Farm, Noke Solar Farmsolar farm | solar farm | 45 | approved, not builtupdated Sep 2025 | Jun 2022 | granted Sep 2025 | Sep 2025 | Cherwell | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Tesco Superstore Bicesterrooftop solar | rooftop solar | 0.6 | under constructionupdated Jul 2020 | Mar 2019 | granted May 2019 | Jul 2020 | Cherwell | 1.2 |
| British Bakels, Granville Wayrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Nov 2022 | Dec 2022 | Cherwell | 1.3 |
| Brita Water Filter Systems Limited, Granville Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Cherwell | 1.3 |
| Bicester Avenue Garden Centre, Oxford Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2022 | Aug 2022 | granted Oct 2022 | Nov 2022 | Cherwell | 1.6 |
| David Lloyd Clubs, Wendlebury Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Cherwell | 1.8 |
| Bicester Park, Charbridge Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2023 | Feb 2023 | granted Mar 2023 | Apr 2023 | Cherwell | 1.8 |
| Units 4, 5, 6, 8 & 9, Longlands Roadrooftop solar | rooftop solar | 0.7 | application submittedupdated Jan 2025 | Oct 2024 | — | Jan 2025 | Cherwell | 2.0 |
| Bicester Hotel Golf And Spa, Akeman Streetrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Cherwell | 2.9 |
| Symmetry Park, Ambrosden - Unit A2 - Solar Panelsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Apr 2025 | Mar 2025 | granted May 2025 | Apr 2025 | Cherwell | 3.2 |
| Pool Farm, Mill Lane, Stratton Solar Farmbattery storage | battery storage | — | approved, not builtupdated Jun 2025 | Jan 2023 | granted May 2025 | Jun 2025 | Cherwell | 4.3 |
| H M Prison Leyhill, Tortworth Solar Photovoltaic PV Panelssolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Jan 2022 | Jan 2022 | granted Jun 2022 | Jan 2022 | Cherwell | 4.7 |
| Arncott Power Generation Plant, Murcott Road Solar Farmsolar farm | solar farm | — | application submittedupdated Nov 2025 | Sep 2025 | — | Nov 2025 | Cherwell | 5.4 |
| Ray Valley Solar Farmbattery storage | battery storage | — | under constructionupdated Jun 2023 | Feb 2020 | granted Aug 2020 | Jun 2023 | Cherwell | 5.8 |
| Moto Hospitality, Stoke Lynerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Cherwell | 6.2 |
| HM Prison Bullingdon - Photovoltaic Panelssolar farm | solar farm | 0.5 | approved, not builtupdated Dec 2022 | Mar 2021 | granted Jun 2021 | Dec 2022 | Cherwell | 6.8 |
Distance from the average position of the OX26 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 2 | 5 | 5 | 0 | 119 |
| Rooftop solar | 10 | 1 | 9 | 0 | 0 | 4.8 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 4 | 1 | 3 | 0 | 0 | 44 |
MW in pipeline: pending, approved and under-construction capacity.
How Cherwell decides solar, wind and battery applications
| Applications | Cherwell | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 44 | 10,236 |
| Refused | 6 (14%) | 19% |
| Solar refused | 3 of 37 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 2 of 6 | 16% |
| Median time from submission to decision | 10.5 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 5 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near OX26, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.