Solar, wind and battery projects near Buckingham (MK18)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of MK18 (Buckinghamshire): 5 are waiting for a planning decision, 12 approved but not yet running, 8 operational. The largest live scheme is East Claydon Substation, East Claydon Road (500 MW battery storage, application submitted on 28 April 2025, no decision recorded), 6.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of MK18
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wipac Group, London Roadrooftop solar | rooftop solar | 1.3 | approved, not builtupdated Jun 2026 | Apr 2026 | granted Jun 2026 | Jun 2026 | Buckinghamshire | 1.3 |
| Manor Farmsolar farm | solar farm | 12 | approved, not built may be out of dateupdated Feb 2023 | Jan 2021 | granted Jun 2022 | Feb 2023 | Buckinghamshire | 2.2 |
| Gawcott Fields Farmsolar farm | solar farm | 9.2 | operationalupdated Apr 2016 | Jul 2014 | granted Oct 2014 | Apr 2016 | Buckinghamshire | 2.7 |
| Land at Thornborough Groundssolar farm | solar farm | 5 | operationalupdated Jul 2018 | Mar 2015 | granted Jun 2015 | Jul 2018 | Buckinghamshire | 4.4 |
| Fox Covert Solar Farmsolar farm | solar farm | 22 | operationalupdated Oct 2023 | Aug 2020 | granted Jun 2021 | Oct 2023 | Buckinghamshire | 5.0 |
| East Claydon Substation, East Claydon Roadbattery storage | battery storage | 500 | application submittedupdated Jul 2025 | Apr 2025 | — | Jul 2025 | Buckinghamshire | 6.1 |
| Thornton Estatesolar farm | solar farm | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Buckinghamshire | 6.1 |
| Tuckey Farmsolar farm | solar farm | 25 | approved, not built may be out of dateupdated Feb 2025 | Mar 2019 | granted Apr 2021 | Feb 2025 | Buckinghamshire | 6.4 |
| Wicken Farm, Leckhampstead Solar Farmsolar farm | solar farm | 21 | approved, not builtupdated Jan 2024 | Jan 2022 | granted Dec 2023 | Jan 2024 | West Northamptonshire | 6.8 |
| Manor Farm, Beachampton Solar Farmsolar farm | solar farm | 25 | approved, not builtupdated Apr 2026 | Oct 2022 | granted Jan 2024 | Apr 2026 | Buckinghamshire | 7.6 |
| East Claydon Battery Energy Storagebattery storage | battery storage | 500 | approved, not builtupdated Sep 2025 | Dec 2023 | refused Dec 2024 | Sep 2025 | Buckinghamshire | 7.9 |
| Stratford Road Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Dec 2021 | Dec 2020 | granted Jan 2022 | Dec 2021 | Buckinghamshire | 8.0 |
| Sparrow Lodge Farmsolar farm | solar farm | 20 | approved, not built may be out of dateupdated May 2023 | Nov 2019 | granted Mar 2021 | May 2023 | West Northamptonshire | 8.1 |
| Stony Energy Storage Facilitybattery storage | battery storage | 79.9 | operationalupdated May 2024 | Jul 2017 | granted Sep 2021 | May 2024 | Buckinghamshire | 8.2 |
| Land At Potash Farmsolar farm | solar farm | 7 | operationalupdated Sep 2015 | Feb 2011 | granted Apr 2011 | Sep 2015 | Buckinghamshire | 8.4 |
| Mount Mill Farmsolar farm | solar farm | 12 | operationalupdated May 2015 | Aug 2014 | granted Sep 2014 | May 2015 | West Northamptonshire | 8.5 |
| Wood End, Mursley Roadsolar farm | solar farm | 36 | approved, not built may be out of dateupdated May 2022 | Jan 2020 | granted Dec 2022 | May 2022 | Buckinghamshire | 8.6 |
| Hogshaw Road, Granboroughbattery storage | battery storage | 99 | application withdrawnupdated Apr 2025 | Dec 2024 | — | Apr 2025 | Buckinghamshire | 8.6 |
| Calvert Landfill Site Solar Arraysolar farm | solar farm | 16 | application submitted may be out of dateupdated Sep 2021 | Mar 2021 | — | Sep 2021 | Buckinghamshire | 8.6 |
| Silver Spinney Farmbattery storage | battery storage | 5 | under constructionupdated Apr 2021 | Jan 2019 | — | Apr 2021 | West Northamptonshire | 9.0 |
| Longbreach Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | Buckinghamshire | 9.2 |
| Oaks Farm Solar Farmsolar farm | solar farm | 37 | approved, not builtupdated Jul 2026 | Jul 2025 | granted May 2026 | Jul 2026 | Buckinghamshire | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Buckingham Tesco Superstorerooftop solar | rooftop solar | 0.2 | operationalupdated Apr 2020 | Mar 2019 | granted Jul 2019 | Apr 2020 | Buckinghamshire | 1.5 |
| The Swan Pool & Leisure Centre, London Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Buckinghamshire | 2.0 |
| University Of Buckingham Campus, Energy Storage Systembattery storage | battery storage | 0.2 | application withdrawnupdated May 2023 | Mar 2023 | — | May 2023 | Buckinghamshire | 2.3 |
| Fox Covert Solar Farmbattery storage | battery storage | — | operationalupdated Oct 2023 | Aug 2020 | granted Jun 2021 | Oct 2023 | Buckinghamshire | 5.1 |
| Noble Foods, Barton Roadrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Buckinghamshire | 5.8 |
Distance from the average position of the MK18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 3 | 8 | 5 | 0 | 297 |
| Rooftop solar | 4 | 1 | 2 | 1 | 0 | 1.6 |
| Battery storage | 7 | 1 | 2 | 2 | 0 | 1,005 |
MW in pipeline: pending, approved and under-construction capacity.
How Buckinghamshire decides solar, wind and battery applications
| Applications | Buckinghamshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 80 | 10,236 |
| Refused | 19 (24%) | 19% |
| Solar refused | 14 of 68 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 3 of 9 | 16% |
| Median time from submission to decision | 15.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 7 | — |
All projects in Buckinghamshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near MK18, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.