Energy Projects Near You

East Claydon Battery Energy Storage (500 MW)

East Claydon Battery Energy Storage is a 500 MW battery storage project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 September 2025, not yet built; the record was last updated on 30 September 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

500 MWbattery storage
approved, not builtstatus in REPD
30 September 2025record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
15 December 2023Application submitted
20 December 2024Refused by the planning authority
11 September 2025Appeal allowed

Project details

Technology
battery storage (stand-alone storage)
Capacity
500 MW
Status (REPD)
approved, not built
Record last updated
30 September 2025
Operator or applicant
Statera Energy
Planning authority
Buckinghamshire
Planning application reference
23/03875/APP
Address (REPD)
Rookery Farm, Granborough, Buckingham
Council area (by location)
Buckinghamshire
Time to decision
53 weeks
REPD reference
15501

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hogshaw Road, Granboroughbattery storage99application withdrawn1.0
Longbreach Solar Farmsolar farm49.9application submitted1.3
Tuckey Farmsolar farm25approved, not built1.6
East Claydon Substation, East Claydon Roadbattery storage500application submitted1.9
Fox Covert Solar Farmsolar farm22operational4.7
Wood End, Mursley Roadsolar farm36approved, not built6.6
Calvert Landfill Site Solar Arraysolar farm16application submitted7.0
Knapps Hook Farmsolar farm8.9application withdrawn7.0
Littleton Green Energy Parksolar farm10application submitted7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.92, -0.9021).