Energy Projects Near You

Wood End, Mursley Road (36 MW solar farm)

Wood End, Mursley Road is a 36 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 December 2022, not yet built; the record was last updated on 20 May 2022. REPD records the planning permission as expiring on 2 December 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWsolar farm
approved, not builtmay be out of datestatus in REPD
20 May 2022record last updated
Buckinghamshirecouncil area

REPD records the planning permission as expiring on 2 December 2025, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
10 January 2020Application submitted
6 May 2022Refused by the planning authority
8 July 2022Appeal lodged
2 December 2022Planning permission granted
2 December 2022Appeal allowed
2 December 2025Permission expired

Project details

Technology
solar farm
Capacity
36 MW
Status (REPD)
approved, not built
Record last updated
20 May 2022
Operator or applicant
Elgin Energy
Planning authority
Buckinghamshire
Planning application reference
19/04485/APP
Appeal reference
APP/J0405/W/22/3302716
Site area
48.2 ha
Address (REPD)
Home Farm, Mursley Road, Little Horwood, Milton Keynes, Buckinghamshire
Council area (by location)
Buckinghamshire
Time to decision
151 weeks
Contracts for Difference
AR5
REPD reference
7605

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fox Covert Solar Farmsolar farm22operational3.9
Salden Wind Farmwind farm10refused4.6
Thornton Estatesolar farm50application submitted4.9
Stratford Road Solar Farmsolar farm5approved, not built5.4
Land At Potash Farmsolar farm7operational5.6
Tuckey Farmsolar farm25approved, not built5.8
Oaks Farm Solar Farmsolar farm37approved, not built5.8
Stony Energy Storage Facilitybattery storage79.9operational5.8
Hogshaw Road, Granboroughbattery storage99application withdrawn6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9677, -0.8449).