Salden Wind Farm (10 MW)

Salden Wind Farm is a 10 MW wind farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 7 August 2015; the record was last updated on 2 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refusedstatus in REPD
2 September 2015record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
12 December 2013Application submitted
7 August 2015Refused by the planning authority

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused
Record last updated
2 September 2015
Operator or applicant
North Bucks Wind Energy Ltd
Planning authority
Buckinghamshire
Planning application reference
13/03455/APP
Turbines
4
Address (REPD)
Land At Cowpasture Farm Drayton Road Newton Longville Buckinghamshire MK17 0BU
Council area (by location)
Buckinghamshire
Time to decision
86 weeks
REPD reference
4239

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dorcas Lane Wind Farmwind farm10refused3.3
Wood End, Mursley Roadsolar farm36approved, not built4.6
Oaks Farm Solar Farmsolar farm37approved, not built7.7
Land At Potash Farmsolar farm7operational8.2
Stratford Road Solar Farmsolar farm5approved, not built8.2
Fox Covert Solar Farmsolar farm22operational8.5
Stony Energy Storage Facilitybattery storage79.9operational8.5
Thornton Estatesolar farm50application submitted8.6
Hogshaw Road, Granboroughbattery storage99application withdrawn9.2