Energy Projects Near You

Stratford Road Solar Farm (5 MW)

Stratford Road Solar Farm is a 5 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 January 2022, not yet built; the record was last updated on 10 December 2021. REPD also records that the planning permission expired on 28 January 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
10 December 2021record last updated
Buckinghamshirecouncil area

REPD also records that the planning permission expired on 28 January 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
16 December 2020Application submitted
28 January 2022Planning permission granted
28 January 2025Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
10 December 2021
Operator or applicant
Rowlandson Organisation Group
Planning authority
Buckinghamshire
Planning application reference
20/04311/APP
Site area
7.8 ha
Address (REPD)
Stratford Road
Council area (by location)
Buckinghamshire
Time to decision
58 weeks
REPD reference
8267

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Potash Farmsolar farm7operational0.4
Stony Energy Storage Facilitybattery storage79.9operational0.4
Manor Farm, Beachampton Solar Farmsolar farm25approved, not built1.2
Oaks Farm Solar Farmsolar farm37approved, not built1.5
Thornton Estatesolar farm50application submitted1.9
Mount Mill Farmsolar farm12operational3.3
Sparrow Lodge Farmsolar farm20approved, not built3.5
Wicken Farm, Leckhampstead Solar Farmsolar farm21approved, not built4.0
Land at Thornborough Groundssolar farm5operational4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0141, -0.8685).