Energy Projects Near You

Solar, wind and battery projects near Milton Keynes (MK19)

64 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of MK19 (West Northamptonshire): 3 are waiting for a planning decision, 36 approved but not yet running, 13 operational. The largest live scheme is Thornton Estate (50 MW solar farm, application submitted on 23 July 2025, no decision recorded), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

64projects within 10 km
3awaiting a decision
36approved, not running
13operational

Projects within 10 km of MK19

Projects of 1 MW and more (24)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Knotwood Fields Farmsolar farmsolar farm2.6permission expiredupdated Aug 2019Sep 2015granted Dec 2015Aug 2019West Northamptonshire1.1
Yardley Road Solar Farmsolar farmsolar farm40application submittedupdated Aug 2025Jun 2025—Aug 2025West Northamptonshire2.4
Silver Spinney Farmbattery storagebattery storage5under constructionupdated Apr 2021Jan 2019—Apr 2021West Northamptonshire4.6
Orchard Way Wind Farmwind farmwind farm15refused on appealupdated Aug 2014Sep 2011refused Nov 2012Aug 2014Milton Keynes4.8
Mount Mill Farmsolar farmsolar farm12operationalupdated May 2015Aug 2014granted Sep 2014May 2015West Northamptonshire4.9
Sparrow Lodge Farmsolar farmsolar farm20approved, not built may be out of dateupdated May 2023Nov 2019granted Mar 2021May 2023West Northamptonshire5.4
Homestead Farm (Alderton)solar farmsolar farm17.6operationalupdated Mar 2016Sep 2014granted Dec 2014Mar 2016West Northamptonshire5.5
Oaks Farm Solar Farmsolar farmsolar farm37approved, not builtupdated Jul 2026Jul 2025granted May 2026Jul 2026Buckinghamshire6.3
Manor Farm, Beachampton Solar Farmsolar farmsolar farm25approved, not builtupdated Apr 2026Oct 2022granted Jan 2024Apr 2026Buckinghamshire6.4
Stonepit Farmsolar farmsolar farm5operationalupdated May 2016Sep 2013granted Dec 2013May 2016West Northamptonshire6.4
Stony Energy Storage Facilitybattery storagebattery storage79.9operationalupdated May 2024Jul 2017granted Sep 2021May 2024Buckinghamshire6.5
Littlewood Farmsolar farmsolar farm14operationalupdated Aug 2015Jun 2014granted Oct 2014Aug 2015Milton Keynes6.6
Land At Potash Farmsolar farmsolar farm7operationalupdated Sep 2015Feb 2011granted Apr 2011Sep 2015Buckinghamshire6.7
Wicken Farm, Leckhampstead Solar Farmsolar farmsolar farm21approved, not builtupdated Jan 2024Jan 2022granted Dec 2023Jan 2024West Northamptonshire6.7
Stratford Road Solar Farmsolar farmsolar farm5approved, not built may be out of dateupdated Dec 2021Dec 2020granted Jan 2022Dec 2021Buckinghamshire7.0
Salcey Green Farmsolar farmsolar farm5refusedupdated Jul 2024Apr 2024refused Jul 2024Jul 2024Milton Keynes7.3
Stoke Heights Wind Farmwind farmwind farm30application withdrawnupdated Feb 2018Jun 2011—Feb 2018Milton Keynes7.6
The Kicklessolar farmsolar farm5operationalupdated Apr 2016May 2014granted Nov 2014Apr 2016Milton Keynes8.0
Mercedes Benz UK Solar array car portrooftop solarrooftop solar2approved, not built may be out of dateupdated Dec 2021Jun 2021granted Sep 2021Dec 2021Milton Keynes8.5
Salcey Solar Farmbattery storagebattery storage1operationalupdated Mar 2019Mar 2016—Mar 2019Milton Keynes8.5
Thornton Estatesolar farmsolar farm50application submittedupdated Sep 2025Jul 2025—Sep 2025Buckinghamshire8.6
Land at Thornborough Groundssolar farmsolar farm5operationalupdated Jul 2018Mar 2015granted Jun 2015Jul 2018Buckinghamshire9.1
Bulls Head Farm Northsolar farmsolar farm4.7operationalupdated Feb 2015Dec 2013granted Apr 2014Feb 2015West Northamptonshire9.2
M1 Wind Farmwind farmwind farm7.2operationalupdated Aug 2014Nov 2011granted May 2013Aug 2014West Northamptonshire9.5
Smaller schemes under 1 MW, mostly rooftop solar (40)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wolverton Swimming And Fitness Centre, Addington Avenuerooftop solarrooftop solar0.4approved, not builtupdated Dec 2025Sep 2025granted Oct 2025Dec 2025Milton Keynes2.9
Wolverton Swimming & Fitness Centre, Addington Avenuebattery storagebattery storage0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Milton Keynes3.1
The Town Hallrooftop solarrooftop solar—refusedupdated Apr 2021Jan 2021refused May 2021Apr 2021Milton Keynes3.5
Burners Lane, Kiln Farmrooftop solarrooftop solar0.5approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Milton Keynes3.7
Hodge Lea Lane, Hodge Leabattery storagebattery storage0.2refusedupdated Feb 2025Nov 2024refused Jan 2025Feb 2025Milton Keynes4.0
Vodafone, Fingle Driverooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Milton Keynes4.2
Ingram Content Group UK, Chapter Houserooftop solarrooftop solar1approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Milton Keynes4.3
Fingle Drive, Grafton Streetbattery storagebattery storage0.2refusedupdated Apr 2025Nov 2024refused Mar 2025Apr 2025Milton Keynes4.4
New Bradwell School, Bounty Streetrooftop solarrooftop solar—approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Milton Keynes4.4
Brioche Pasquier UK, Garamonde Drive Solar Canopiesrooftop solarrooftop solar0.6approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025Milton Keynes5.0
Brioche Pasquier, Garamonde Driverooftop solarrooftop solar0.9refusedupdated May 2024Mar 2024refused May 2024May 2024Milton Keynes5.3
Alston Drive, Bradwell Abbey - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Milton Keynes5.3
Stone Hill Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025Milton Keynes5.5
Volkswagen Group UK, Garamonde Driverooftop solarrooftop solar0.7approved, not builtupdated Dec 2025Sep 2024granted Jan 2025Dec 2025Milton Keynes5.5
The Church Of The Latterday Saints, The High Streetbattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Milton Keynes5.8
Bradwell Road - Micro Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Milton Keynes6.3
Bradwell Road, Loughton Lodgerooftop solarrooftop solar0.5approved, not builtupdated Jun 2022Apr 2022granted Jun 2022Jun 2022Milton Keynes6.4
Deltic Avenue, Rooksleyrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Milton Keynes6.4
Paynes Drive & Linceslade Grove, Loughton - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Apr 2025Nov 2024refused Feb 2025Apr 2025Milton Keynes6.8
Linford Wood Business Park, Linford Woodrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Milton Keynes6.9
The Hazeley Academyrooftop solarrooftop solar0.2operationalupdated Oct 2019Feb 2019granted May 2020Oct 2019Milton Keynes7.0
St Leger Drive, Great Linford - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Nov 2024granted Feb 2025Apr 2025Milton Keynes7.0
Wolverton Road, Giffard Park Roundabout - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated Feb 2025Feb 2025—Feb 2025Milton Keynes7.5
Tanners Drive, Blakelandsrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Milton Keynes7.6
Falcon Projectbattery storagebattery storage0.3operationalupdated Oct 2018——Oct 2018Milton Keynes7.7
Yeomans Drive, Blakelands - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025Milton Keynes8.1
Paxton Crescent, Ackroyd Place - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025Milton Keynes8.2
Duckworth Court, Oldbrook Boulevard - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Dec 2024granted Mar 2025Apr 2025Milton Keynes8.3
Kelvin Drive - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Milton Keynes8.4
Winterhill Houserooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Milton Keynes8.6
Delaware Drive, Tongwellrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025Milton Keynes8.6
David Lloyd, Livingstone Driverooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Milton Keynes8.8
Brickhill Street, Lakeside Roundabout - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Milton Keynes9.0
Verge In Woughton Leisure Centre - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Milton Keynes9.0
The Milton Keynes Academy, Fulwoods Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Milton Keynes9.1
Pear Tree Lane, Bleak Hall - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Apr 2025Nov 2024granted Feb 2025Apr 2025Milton Keynes9.2
Caldecote Farm - Storage & Distribution Unitrooftop solarrooftop solar0.3under constructionupdated Jan 2025Sep 2021granted Jul 2023Jan 2025Milton Keynes9.5
Whittlebury Park Golf & Country Club, High Streetrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Jan 2023granted Mar 2023Mar 2023West Northamptonshire9.7
Snelshall Street, Tattenhoebattery storagebattery storage0.2application withdrawnupdated Nov 2025Jul 2025—Nov 2025Milton Keynes9.7
Whittlebury Park, High Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2022Jul 2022granted Aug 2022Jul 2022West Northamptonshire9.8

Distance from the average position of the MK19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm172581198
Rooftop solar22019129.2
Wind farm300110
Battery storage22112337.4

MW in pipeline: pending, approved and under-construction capacity.

How West Northamptonshire decides solar, wind and battery applications

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

All projects in West Northamptonshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near MK19, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.