Stonepit Farm (5 MW solar farm)

Stonepit Farm is a 5 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 July 2014; the record was last updated on 10 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
10 May 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
16 September 2013Application submitted
24 December 2013Planning permission granted
28 May 2014Construction started
28 July 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
10 May 2016
Operator or applicant
Lark Energy
Planning authority
West Northamptonshire
Planning application reference
S/2013/1201/MAF
Site area
41.9 ha
Address (REPD)
Stonepit Farm Hanslope Road Hartwell
Council area (by location)
West Northamptonshire
Time to decision
14 weeks
REPD reference
2364

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Salcey Green Farmsolar farm5refused1.3
Littlewood Farmsolar farm14operational3.0
M1 Wind Farmwind farm7.2operational3.3
Stoke Heights Wind Farmwind farm30application withdrawn4.5
Homestead Farm (Alderton)solar farm17.6operational6.3
Salcey Solar Farmsolar farm5operational6.3
Yardley Road Solar Farmsolar farm40application submitted6.4
Manor Farm (Horton)solar farm5operational6.5
Orchard Way Wind Farmwind farm15refused on appeal6.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1339, -0.8471).