Salcey Solar Farm (5 MW)

Salcey Solar Farm is a 5 MW solar farm project in Milton Keynes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 25 September 2014; the record was last updated on 4 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
4 July 2018record last updated
Milton Keynescouncil area

Planning timeline

DateStage
2 December 2013Application submitted
7 March 2014Planning permission granted
1 June 2014Construction started
25 September 2014Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
4 July 2018
Operator or applicant
NextEnergy Capital
Planning authority
Milton Keynes
Planning application reference
13/02504/FUL
Site area
11.0 ha
Address (REPD)
Bulls Head Farm, Eakley Lanes, Stoke Goldington, Newport Pagnell, Buckinghamshire
Council area (by location)
Milton Keynes
Time to decision
14 weeks
REPD reference
1878

Who decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoke Heights Wind Farmwind farm30application withdrawn2.7
Manor Farm (Horton)solar farm5operational3.6
Littlewood Farmsolar farm14operational4.0
Rectory Farm/Embertonsolar farm9operational4.5
Hyde Farmsolar farm5operational4.9
Milton Keynes Wind Farmwind farm14operational5.0
Salcey Green Farmsolar farm5refused5.1
The Kicklessolar farm5operational5.7
Stonepit Farmsolar farm5operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1466, -0.7565).