The Kickles (5 MW solar farm)

The Kickles is a 5 MW solar farm project in Milton Keynes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 22 March 2016; the record was last updated on 22 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 April 2016record last updated
Milton Keynescouncil area

Planning timeline

DateStage
22 May 2014Application submitted
7 November 2014Planning permission granted
25 November 2015Construction started
22 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 April 2016
Operator or applicant
Green Energy UK Direct Ltd/ Vogt Solar
Planning authority
Milton Keynes
Planning application reference
14/01068/FUL
Site area
13.3 ha
Address (REPD)
The Kickles Lakes Lane Newport Pagnell
Council area (by location)
Milton Keynes
Time to decision
24 weeks
REPD reference
2319

Who decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Orchard Way Wind Farmwind farm15refused on appeal3.2
Stoke Heights Wind Farmwind farm30application withdrawn4.4
Littlewood Farmsolar farm14operational5.4
Milton Keynes Wind Farmwind farm14operational5.6
Rectory Farm/Embertonsolar farm9operational5.7
Salcey Solar Farmsolar farm5operational5.7
Salcey Green Farmsolar farm5refused7.7
Stonepit Farmsolar farm5operational8.3
Manor Farm (Horton)solar farm5operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0962, -0.7429).