Manor Farm (Horton) (5 MW solar farm)

Manor Farm (Horton) is a 5 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 April 2016; the record was last updated on 31 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
31 May 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
25 July 2014Application submitted
21 November 2014Planning permission granted
3 February 2016Construction started
15 April 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
31 May 2016
Operator or applicant
Capital Stage
Planning authority
West Northamptonshire
Planning application reference
S/2014/1289/MAF
Site area
11.4 ha
Address (REPD)
Land at Manor Farm Ravenstone Lane Horton
Council area (by location)
West Northamptonshire
Time to decision
17 weeks
REPD reference
2205

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Salcey Solar Farmsolar farm5operational3.6
Salcey Green Farmsolar farm5refused5.2
Preston, Deanery Solar Farmsolar farm27.8application submitted5.2
Hyde Farmsolar farm5operational5.3
Stoke Heights Wind Farmwind farm30application withdrawn5.3
Littlewood Farmsolar farm14operational5.7
M1 Wind Farmwind farm7.2operational5.7
Stonepit Farmsolar farm5operational6.5
Nunn Woodwind farm24application withdrawn7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1752, -0.7804).