Energy Projects Near You

Hyde Farm (5 MW solar farm)

Hyde Farm is a 5 MW solar farm project in Milton Keynes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 March 2017; the record was last updated on 26 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 April 2017record last updated
Milton Keynescouncil area

Planning timeline

DateStage
7 August 2015Application submitted
12 January 2016Planning permission granted
16 December 2016Construction started
16 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 April 2017
Operator or applicant
Conergy
Planning authority
Milton Keynes
Planning application reference
15/01791/FUL
Site area
11.5 ha
Address (REPD)
Hyde Farm, Warrington Road, Olney
Council area (by location)
Milton Keynes
Time to decision
23 weeks
REPD reference
5685

Who decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nunn Woodwind farm24application withdrawn2.3
Rectory Farm/Embertonsolar farm9operational4.5
Salcey Solar Farmsolar farm5operational4.9
Milton Keynes Wind Farmwind farm14operational5.0
Manor Farm (Horton)solar farm5operational5.3
Nun Wood (Milton Keynes)wind farm9refused on appeal5.5
Nun Wood (Wellingborough)wind farm9refused on appeal5.5
Nun Wood (Bedford)wind farm18refused on appeal6.1
Grendon Storagebattery storage49.9permission expired7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1763, -0.7033).