Nun Wood (Bedford) (18 MW wind farm)

Nun Wood (Bedford) is an 18 MW wind farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 17 December 2013; the record was last updated on 31 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18 MWwind farm
refused on appealstatus in REPD
31 January 2014record last updated
Bedfordcouncil area

Planning timeline

DateStage
29 January 2009Application submitted
15 February 2011Refused by the planning authority
17 December 2013Appeal refused

Project details

Technology
wind farm
Capacity
18 MW
Status (REPD)
refused on appeal
Record last updated
31 January 2014
Operator or applicant
Npower Renewables
Planning authority
Bedford
Planning application reference
09/00137/MAF
Appeal reference
K0235/A/11/2149434
Turbines
6
Address (REPD)
Land West Of New Road (Nun Wood) Harrold Bedfordshire
Council area (by location)
Bedford
Time to decision
107 weeks
REPD reference
3773

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Wood Roadsolar farm5refused1.4
Nun Wood (Milton Keynes)wind farm9refused on appeal2.1
Nun Wood (Wellingborough)wind farm9refused on appeal2.9
Odell Glebe Solar Farmsolar farm16.8operational3.7
Airfield Farm (Podington)wind farm8.6operational3.7
Nunn Woodwind farm24application withdrawn3.8
Glebe Farm Solar Energy Parksolar farm15operational5.9
Hyde Farmsolar farm5operational6.1
Goosey Lodge Solar Farmsolar farm10.5approved, not built6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2047, -0.6274).