Energy Projects Near You

Land at Wood Road (5 MW solar farm)

Land at Wood Road is a 5 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 27 July 2015; the record was last updated on 5 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
5 August 2015record last updated
Bedfordcouncil area

Planning timeline

DateStage
10 March 2015Application submitted
27 July 2015Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
5 August 2015
Operator or applicant
Town Farm Solar Farm
Planning authority
Bedford
Planning application reference
15/00444/MAF
Site area
13.5 ha
Address (REPD)
Land At Wood Road, Harrold, Bedford, Bedfordshire,
Council area (by location)
Bedford
Time to decision
20 weeks
REPD reference
5057

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nun Wood (Bedford)wind farm18refused on appeal1.4
Odell Glebe Solar Farmsolar farm16.8operational2.3
Airfield Farm (Podington)wind farm8.6operational2.4
Nun Wood (Milton Keynes)wind farm9refused on appeal2.5
Nun Wood (Wellingborough)wind farm9refused on appeal3.1
Glebe Farm Solar Energy Parksolar farm15operational4.6
Nunn Woodwind farm24application withdrawn5.0
Goosey Lodge Solar Farmsolar farm10.5approved, not built5.5
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2152, -0.6171).