Odell Glebe Solar Farm (16.8 MW)

Odell Glebe Solar Farm is a 16.8 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.8 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Bedfordcouncil area

Planning timeline

DateStage
26 June 2014Application submitted
22 September 2014Planning permission granted
22 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
16.8 MW
Status (REPD)
operational
Record last updated
15 April 2015
Operator or applicant
Vento Ludens
Planning authority
Bedford
Planning application reference
14/01333/MAF
Site area
43.3 ha
Address (REPD)
Land At The Old Airfield Site Podington Airfield Airfield Road (Odell Glebe Solar Farm) Podington
Council area (by location)
Bedford
Time to decision
13 weeks
REPD reference
2152

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Airfield Farm (Podington)wind farm8.6operational1.0
Land at Wood Roadsolar farm5refused2.3
Glebe Farm Solar Energy Parksolar farm15operational2.4
Goosey Lodge Solar Farmsolar farm10.5approved, not built3.3
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built3.4
Nun Wood (Bedford)wind farm18refused on appeal3.7
Nun Wood (Milton Keynes)wind farm9refused on appeal4.3
Nun Wood (Wellingborough)wind farm9refused on appeal4.7
Vicarage Farmbattery storage50refused7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2317, -0.5968).