Vicarage Farm (50 MW battery storage)

Vicarage Farm is a 50 MW battery storage project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 18 December 2025; the record was last updated on 6 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
refusedstatus in REPD
6 January 2026record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
24 July 2025Application submitted
18 December 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
refused
Record last updated
6 January 2026
Operator or applicant
Enray Power Limited
Planning authority
North Northamptonshire
Planning application reference
NW/25/00405/FUL
Address (REPD)
Opp Caravan Site, Gipsy Lane, Irchester, Wellingborough
Council area (by location)
North Northamptonshire
Time to decision
21 weeks
Name in REPD
Vicarage Farm - Battery Energy Storage System
REPD reference
19771

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
London Road, Irchester Solar Farmsolar farm26operational1.0
Wellingborough Solar Farmsolar farm8.5operational1.6
Grendon Storagebattery storage49.9permission expired4.3
Grendon Lakes, Grendonbattery storage50approved, not built4.3
Grendon Road, Earls Bartonbattery storage99.9approved, not built5.2
Quarry, Ditchford Lane Solar Farmsolar farm10approved, not built5.4
Nun Wood (Wellingborough)wind farm9refused on appeal5.8
Airfield Farm (Podington)wind farm8.6operational6.0
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2709, -0.6772).