Energy Projects Near You

Grendon Storage (49.9 MW)

Grendon Storage is a 49.9 MW battery storage project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 1 May 2021; the record was last updated on 21 August 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
permission expiredstatus in REPD
21 August 2020record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
28 September 2017Application submitted
20 November 2017Planning permission granted
1 May 2021Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
permission expired
Record last updated
21 August 2020
Operator or applicant
Statera Energy / Grendon Storage
Planning authority
North Northamptonshire
Planning application reference
WP/17/00602/FUL
Address (REPD)
Field South East Of Sub Statio, Station Road, Grendon, Wellingborough, Northampton, Northamptonshire
Council area (by location)
North Northamptonshire
Time to decision
8 weeks
REPD reference
7089

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grendon Lakes, Grendonbattery storage50approved, not built0.8
Grendon Road, Earls Bartonbattery storage99.9approved, not built2.7
Nun Wood (Wellingborough)wind farm9refused on appeal4.1
Vicarage Farmbattery storage50refused4.3
Wellingborough Solar Farmsolar farm8.5operational4.9
Nun Wood (Milton Keynes)wind farm9refused on appeal4.9
London Road, Irchester Solar Farmsolar farm26operational5.3
Nunn Woodwind farm24application withdrawn6.0
Green Hill Solar Farm & Battery Storagesolar farm600application submitted6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2392, -0.7137).