Solar, wind and battery projects near Olney (MK46)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of MK46 (Milton Keynes): 2 are waiting for a planning decision, 9 approved but not yet running, 10 operational. The largest live scheme is Grendon Lakes, Grendon (50 MW battery storage, approved on 29 July 2025, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of MK46
Projects of 1 MW and more (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Hyde Farmsolar farm | solar farm | 5 | operationalupdated Apr 2017 | Aug 2015 | granted Jan 2016 | Apr 2017 | Milton Keynes | 2.2 |
| Rectory Farm/Embertonsolar farm | solar farm | 9 | operationalupdated Apr 2015 | Feb 2014 | granted Sep 2014 | Apr 2015 | Milton Keynes | 2.3 |
| Milton Keynes Wind Farmwind farm | wind farm | 14 | operationalupdated Dec 2017 | Aug 2006 | granted Jan 2008 | Dec 2017 | Milton Keynes | 2.8 |
| Salcey Solar Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Dec 2013 | granted Mar 2014 | Jul 2018 | Milton Keynes | 3.9 |
| Nunn Woodwind farm | wind farm | 24 | application withdrawnupdated Oct 2013 | — | — | Oct 2013 | Milton Keynes | 4.1 |
| Manor Farm (Horton)solar farm | solar farm | 5 | operationalupdated May 2016 | Jul 2014 | granted Nov 2014 | May 2016 | West Northamptonshire | 5.8 |
| Stoke Heights Wind Farmwind farm | wind farm | 30 | application withdrawnupdated Feb 2018 | Jun 2011 | — | Feb 2018 | Milton Keynes | 6.4 |
| The Kicklessolar farm | solar farm | 5 | operationalupdated Apr 2016 | May 2014 | granted Nov 2014 | Apr 2016 | Milton Keynes | 7.3 |
| Nun Wood (Milton Keynes)wind farm | wind farm | 9 | refused on appealupdated Jan 2014 | Jan 2009 | refused May 2009 | Jan 2014 | North Northamptonshire | 7.3 |
| Nun Wood (Bedford)wind farm | wind farm | 18 | refused on appealupdated Jan 2014 | Jan 2009 | refused Feb 2011 | Jan 2014 | Bedford | 7.4 |
| Salcey Solar Farmbattery storage | battery storage | 1 | operationalupdated Mar 2019 | Mar 2016 | — | Mar 2019 | Milton Keynes | 7.4 |
| Bulls Head Farm Northsolar farm | solar farm | 4.7 | operationalupdated Feb 2015 | Dec 2013 | granted Apr 2014 | Feb 2015 | West Northamptonshire | 7.5 |
| Nun Wood (Wellingborough)wind farm | wind farm | 9 | refused on appealupdated Jan 2014 | Dec 2008 | refused Nov 2011 | Jan 2014 | North Northamptonshire | 7.5 |
| Littlewood Farmsolar farm | solar farm | 14 | operationalupdated Aug 2015 | Jun 2014 | granted Oct 2014 | Aug 2015 | Milton Keynes | 7.8 |
| Land East of Horton Roadsolar farm | solar farm | 4.9 | operationalupdated Jul 2018 | Oct 2014 | granted May 2015 | Jul 2018 | West Northamptonshire | 8.4 |
| Land at Wood Roadsolar farm | solar farm | 5 | refusedupdated Aug 2015 | Mar 2015 | refused Jul 2015 | Aug 2015 | Bedford | 8.7 |
| Snakes Meadow Solar Farmsolar farm | solar farm | 45.5 | approved, not builtupdated Jun 2026 | Oct 2021 | granted May 2024 | Jun 2026 | Bedford | 8.8 |
| Salcey Green Farmsolar farm | solar farm | 5 | refusedupdated Jul 2024 | Apr 2024 | refused Jul 2024 | Jul 2024 | Milton Keynes | 9.0 |
| Grendon Storagebattery storage | battery storage | 49.9 | permission expiredupdated Aug 2020 | Sep 2017 | granted Nov 2017 | Aug 2020 | North Northamptonshire | 9.2 |
| Orchard Way Wind Farmwind farm | wind farm | 15 | refused on appealupdated Aug 2014 | Sep 2011 | refused Nov 2012 | Aug 2014 | Milton Keynes | 9.7 |
| Grendon Lakes, Grendonbattery storage | battery storage | 50 | approved, not builtupdated May 2026 | Jun 2023 | granted Jul 2025 | May 2026 | North Northamptonshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lavendon Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 | Milton Keynes | 0.7 |
| Olney Road, Harvey Drive - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Mar 2025 | May 2025 | Milton Keynes | 1.8 |
| Home Farm, Bedford Road Solar Power Arraysolar farm | solar farm | 0.3 | refusedupdated Jun 2023 | Nov 2022 | refused May 2023 | Jun 2023 | Milton Keynes | 4.2 |
| Station Farmsolar farm | solar farm | 0.1 | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | West Northamptonshire | 7.1 |
| Horton Lodge Farmsolar farm | solar farm | 0.1 | approved, not built may be out of dateupdated Nov 2022 | Jul 2022 | granted Oct 2022 | Nov 2022 | West Northamptonshire | 8.2 |
| Wolverton Road, Giffard Park Roundabout - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Feb 2025 | Feb 2025 | — | Feb 2025 | Milton Keynes | 9.1 |
| Tanners Drive, Blakelandsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Milton Keynes | 9.2 |
| Caldecote Farm - Storage & Distribution Unitrooftop solar | rooftop solar | 0.3 | under constructionupdated Jan 2025 | Sep 2021 | granted Jul 2023 | Jan 2025 | Milton Keynes | 9.4 |
| Yeomans Drive, Blakelands - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Mar 2025 | May 2025 | Milton Keynes | 9.7 |
| Delaware Drive, Tongwellrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Milton Keynes | 9.9 |
Distance from the average position of the MK46 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 0 | 3 | 8 | 3 | 45.8 |
| Rooftop solar | 4 | 1 | 3 | 0 | 0 | 1.1 |
| Wind farm | 7 | 0 | 0 | 1 | 4 | 0 |
| Battery storage | 6 | 1 | 3 | 1 | 0 | 50.6 |
MW in pipeline: pending, approved and under-construction capacity.
How Milton Keynes decides solar, wind and battery applications
| Applications | Milton Keynes | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 77 | 10,236 |
| Refused | 10 (13%) | 19% |
| Solar refused | 4 of 49 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 5 of 26 | 16% |
| Median time from submission to decision | 7.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near MK46, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.