Grendon Lakes, Grendon (50 MW battery storage)

Grendon Lakes, Grendon is a 50 MW battery storage project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 July 2025, not yet built; the record was last updated on 19 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
19 May 2026record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
29 June 2023Application submitted
29 July 2025Planning permission granted
29 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
19 May 2026
Operator or applicant
Statera Energy
Planning authority
North Northamptonshire
Planning application reference
NW/23/00360/FUL
Address (REPD)
Grendon Lakes, Main Road, Grendon, Northampton
Council area (by location)
North Northamptonshire
Time to decision
109 weeks
Name in REPD
Grendon Lakes, Grendon - Battery Storage Facility
REPD reference
14321

Earlier applications for this site

ApplicationMWSubmittedOutcome
Grendon Lakes NW/21/00623/FUL49.915 July 2021refused 30 September 2021
Grendon Lakes, Grendon NW/22/00198/FUL5025 March 2022refused 11 January 2023

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grendon Storagebattery storage49.9permission expired0.8
Grendon Road, Earls Bartonbattery storage99.9approved, not built1.9
Vicarage Farmbattery storage50refused4.3
Wellingborough Solar Farmsolar farm8.5operational4.6
Nun Wood (Wellingborough)wind farm9refused on appeal5.0
London Road, Irchester Solar Farmsolar farm26operational5.3
Nun Wood (Milton Keynes)wind farm9refused on appeal5.7
Green Hill Solar Farm & Battery Storagesolar farm600application submitted6.0
Nunn Woodwind farm24application withdrawn6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.244, -0.7228).