Nun Wood (Wellingborough) (9 MW wind farm)

Nun Wood (Wellingborough) is a 9 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 17 December 2013; the record was last updated on 31 January 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9 MWwind farm
refused on appealstatus in REPD
31 January 2014record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
31 December 2008Application submitted
15 November 2011Refused by the planning authority
17 December 2013Appeal refused

Project details

Technology
wind farm
Capacity
9 MW
Status (REPD)
refused on appeal
Record last updated
31 January 2014
Operator or applicant
Npower Renewables
Planning authority
North Northamptonshire
Planning application reference
WP/2008/0603
Appeal reference
K0235/A/11/2149434
Turbines
3
Address (REPD)
Harrold Road Bozeat Wellingborough Northamptonshire NN29 7LP
Council area (by location)
North Northamptonshire
Time to decision
150 weeks
REPD reference
3774

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Nun Wood (Milton Keynes)wind farm9refused on appeal0.8
Nun Wood (Bedford)wind farm18refused on appeal2.9
Land at Wood Roadsolar farm5refused3.1
Nunn Woodwind farm24application withdrawn3.4
Airfield Farm (Podington)wind farm8.6operational4.1
Grendon Storagebattery storage49.9permission expired4.1
Odell Glebe Solar Farmsolar farm16.8operational4.7
Grendon Lakes, Grendonbattery storage50approved, not built5.0
Hyde Farmsolar farm5operational5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2193, -0.6623).