Energy Projects Near You

Grendon Road, Earls Barton (99.9 MW battery storage)

Grendon Road, Earls Barton is a 99.9 MW battery storage project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 March 2026, not yet built; the record was last updated on 31 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtstatus in REPD
31 March 2026record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
18 August 2025Application submitted
16 March 2026Planning permission granted
16 March 2029Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
31 March 2026
Operator or applicant
Greenfield Energy Developments Limited
Planning authority
North Northamptonshire
Planning application reference
NW/25/00360/FUL
Address (REPD)
301 Grendon Road, Earls Barton, Northampton
Council area (by location)
North Northamptonshire
Time to decision
30 weeks
Name in REPD
Grendon Road, Earls Barton - Battery Energy Storage System
REPD reference
19050

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grendon Lakes, Grendonbattery storage50approved, not built1.9
Grendon Storagebattery storage49.9permission expired2.7
Green Hill Solar Farm & Battery Storagesolar farm600application submitted4.4
Wellingborough Solar Farmsolar farm8.5operational4.8
Vicarage Farmbattery storage50refused5.2
London Road, Irchester Solar Farmsolar farm26operational6.0
Sywell Roadsolar farm5operational6.0
Nun Wood (Wellingborough)wind farm9refused on appeal6.9
Nun Wood (Milton Keynes)wind farm9refused on appeal7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2528, -0.7473).