Energy Projects Near You

Sywell Road (5 MW solar farm)

Sywell Road is a 5 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2017; the record was last updated on 5 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
5 July 2018record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
5 June 2014Application submitted
29 October 2014Planning permission granted
18 December 2015Construction started
23 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
5 July 2018
Operator or applicant
NESF (formerly Lark Energy)
Planning authority
North Northamptonshire
Planning application reference
WP/14/00368/FUL
Site area
24.2 ha
Address (REPD)
Land off, Sywell Road, Mears Ashby, Northampton, Northamptonshire
Council area (by location)
North Northamptonshire
Time to decision
21 weeks
REPD reference
1910

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Hill Solar Farm & Battery Storagesolar farm600application submitted1.6
Stonebrig Lanesolar farm18.8refused3.3
Hall Farm (Hannington)solar farm10.9permission expired4.8
Grendon Road, Earls Bartonbattery storage99.9approved, not built6.0
Wellingborough Solar Farmsolar farm8.5operational6.2
Grendon Lakes, Grendonbattery storage50approved, not built7.6
Vicarage Farmbattery storage50refused7.7
London Road, Irchester Solar Farmsolar farm26operational7.8
Brixworth Landfill, Scaldwell Road Solar Array & Battery Storagesolar farm5.6application submitted8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3033, -0.7775).