Stonebrig Lane (18.8 MW solar farm)

Stonebrig Lane is an 18.8 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 29 October 2014; the record was last updated on 6 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.8 MWsolar farm
refusedstatus in REPD
6 November 2014record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
4 June 2014Application submitted
29 October 2014Refused by the planning authority

Project details

Technology
solar farm
Capacity
18.8 MW
Status (REPD)
refused
Record last updated
6 November 2014
Operator or applicant
JBM Solutions Limited
Planning authority
North Northamptonshire
Planning application reference
WP/14/00359/FUL
Site area
31.6 ha
Address (REPD)
Land At Stonebrig Lane Hardwick Road Little Harrowden Wellingborough Northamptonshire
Council area (by location)
North Northamptonshire
Time to decision
21 weeks
REPD reference
1853

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sywell Roadsolar farm5operational3.3
Green Hill Solar Farm & Battery Storagesolar farm600application submitted4.2
Hall Farm (Hannington)solar farm10.9permission expired5.0
Wellingborough Solar Farmsolar farm8.5operational6.2
Burton Wold Wind Farm Southwind farm7.5operational6.8
Burton Wold Wind Farm Extension (Southern)wind farm8.6abandoned7.1
Latimer Solar Parksolar farm5approved, not built7.1
Burton Wold Solar Farmsolar farm8.4permission expired7.1
Top Lodge Solar Farmsolar farm5permission expired7.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3264, -0.7468).