Solar, wind and battery projects near Kettering (NN16)

49 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NN16 (North Northamptonshire): 16 are waiting for a planning decision, 18 approved but not yet running, 5 operational. The largest live scheme is Brigstock Solar Farm (49.9 MW solar farm, approved on 14 January 2022, not yet built; REPD status may be out of date), 6.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49projects within 10 km
16awaiting a decision
18approved, not running
5operational

Projects within 10 km of NN16

Projects of 1 MW and more (25)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Camgrain Store, Newton Roadwind turbinewind turbine1application submittedupdated Nov 2025Oct 2024—Nov 2025North Northamptonshire4.5
Grafton Underwoodsolar farmsolar farm38approved, not built may be out of dateupdated Jun 2024Aug 2019granted Sep 2020Jun 2024North Northamptonshire4.6
Camgrain Store, Newton Roadwind turbinewind turbine1application submitted may be out of dateupdated Jul 2024Jun 2024—Jul 2024North Northamptonshire4.6
Solar PV Panelssolar farmsolar farm39application submittedupdated Dec 2024Nov 2024—Dec 2024North Northamptonshire4.7
Oakley Bush Solar Farmbattery storagebattery storage10application submittedupdated Dec 2024Nov 2024—Dec 2024North Northamptonshire4.7
Bryant Field Solar Parksolar farmsolar farm5permission expiredupdated May 2020Jun 2015granted Jul 2015May 2020North Northamptonshire5.1
Wold Cottage Solar Farmsolar farmsolar farm5approved, not built may be out of dateupdated May 2020Jun 2015granted Jul 2015May 2020North Northamptonshire5.4
Burton Wold Solar Farmsolar farmsolar farm8.4permission expiredupdated May 2020Feb 2015granted Apr 2015May 2020North Northamptonshire5.5
Windmill Solar Farmsolar farmsolar farm5permission expiredupdated May 2020Jun 2015granted Jul 2015May 2020North Northamptonshire5.5
Top Lodge Solar Farmsolar farmsolar farm5permission expiredupdated May 2020Jun 2015granted Jul 2015May 2020North Northamptonshire5.5
Latimer Solar Parksolar farmsolar farm5approved, not built may be out of dateupdated May 2020Jun 2015granted Aug 2015May 2020North Northamptonshire5.5
Brigstock Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated May 2023Feb 2020granted Jan 2022May 2023North Northamptonshire6.0
New Albion Wind Farmwind farmwind farm14.4operationalupdated Aug 2016Aug 2009granted Jan 2010Aug 2016North Northamptonshire6.0
Burton Wold Wind Farm - Northern Extensionwind farmwind farm14.4operationalupdated Dec 2015Aug 2012granted Nov 2012Dec 2015North Northamptonshire6.2
Burton Wold Windfarmwind farmwind farm20operationalupdated Dec 2017Mar 2004granted Mar 2004Dec 2017North Northamptonshire6.6
Burton Wold Solar Farm - Site Asolar farmsolar farm19.5permission expiredupdated May 2020Aug 2014granted Oct 2014May 2020North Northamptonshire6.7
Burton Wold Wind Farm Southwind farmwind farm7.5operationalupdated Apr 2017Feb 2015granted Mar 2015Apr 2017North Northamptonshire6.7
Burton Wold Wind Farm Extension (Southern)wind farmwind farm8.6abandonedupdated Nov 2016Aug 2011granted Apr 2012Nov 2016North Northamptonshire7.2
Gaultney Solar Parksolar farmsolar farm20.5operationalupdated Oct 2016Jun 2014granted Sep 2014Oct 2016North Northamptonshire7.8
West Lodge Farm Solar Arraysolar farmsolar farm1.2application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire8.8
Solar Photovoltaic Panelssolar farmsolar farm39.3application submittedupdated Aug 2025Jul 2025—Aug 2025North Northamptonshire9.0
Stonebrig Lanesolar farmsolar farm18.8refusedupdated Nov 2014Jun 2014refused Oct 2014Nov 2014North Northamptonshire9.1
RAF Desboroughsolar farmsolar farm49.9permission expiredupdated Feb 2020Apr 2015granted Aug 2015Feb 2020North Northamptonshire9.2
VPK Desborough, Stoke Albany Road, Desborough Solar PV Arraysrooftop solarrooftop solar1.9approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025North Northamptonshire9.6
Barnwell Manor Wind Farmwind farmwind farm10refused on appealupdated Mar 2014Feb 2010refused Jan 2011Mar 2014North Northamptonshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (24)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Kettering Buccleuch Academy, Weekley Glebe Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026North Northamptonshire0.8
Sainsburys, Rockingham Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025North Northamptonshire1.3
Morrisons Supermarket, Lower Streetrooftop solarrooftop solar0.4approved, not builtupdated Sep 2025Mar 2025granted May 2025Sep 2025North Northamptonshire1.6
Belgrave Retail Park, Northfield Avenuerooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026North Northamptonshire1.9
North Kettering Business Park, Hipwell Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Sep 2023granted Oct 2023Nov 2023North Northamptonshire2.3
North Kettering Business Park, Hipwell Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023North Northamptonshire2.3
Kettering Dc1, Hipwell Roadrooftop solarrooftop solar0.8approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023North Northamptonshire2.6
Kettering Leisure Village, Thurston Driverooftop solarrooftop solar0.4application submittedupdated Mar 2026Feb 2026—Mar 2026North Northamptonshire2.6
Glendon Wood Hospital, Prologis Park - Micro Energy Storage Systembattery storagebattery storage0.2application submittedMay 2026——North Northamptonshire2.7
Prologis Park, Unit 2, Glendon Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Feb 2025granted Mar 2025Sep 2025North Northamptonshire3.1
Kettering Energy Parksolar farmsolar farm—application submittedupdated May 2025Mar 2025—May 2025North Northamptonshire5.5
Kettering Energy Parkbattery storagebattery storage—application submittedupdated May 2025Mar 2025—May 2025North Northamptonshire5.5
Wold Road (land south of) Peak Power Generation Plantbattery storagebattery storage—permission expiredupdated May 2020Sep 2015—May 2020North Northamptonshire6.3
Old Head Wood, Brigstockbattery storagebattery storage—approved, not builtupdated Apr 2024Jul 2022granted Mar 2024Apr 2024North Northamptonshire6.4
Uppingham Road - Micro Energy Storage Systembattery storagebattery storage0.2application submittedupdated Jan 2026Nov 2025—Jan 2026North Northamptonshire6.6
Gainsborough Road, Oakley Road - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Mar 2026—May 2026North Northamptonshire8.8
Midlands Logistics Park, Plantation Lanerooftop solarrooftop solar0.5approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026North Northamptonshire8.8
West Lodge Farm, Pipewell Roadsolar farmsolar farm0.9application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire8.8
West Lodge Rural Centre, Back Lanerooftop solarrooftop solar0.2application submittedupdated Nov 2024Oct 2024—Nov 2024North Northamptonshire8.8
West Lodge Farm Solar Arraybattery storagebattery storage—application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire8.8
Tower Hill Roadbattery storagebattery storage0.2approved, not builtupdated Apr 2026Nov 2025granted Feb 2026Apr 2026North Northamptonshire9.1
Corby East Midlands International Pool, Parkland Gatewayrooftop solarrooftop solar0.3approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024North Northamptonshire9.3
Cottingham Road - Micro Energy Storage Projectbattery storagebattery storage0.2application submittedupdated Mar 2026Jan 2026—Mar 2026North Northamptonshire9.5
Unit 2, Enterprise Court Battery Energy Storage Unitbattery storagebattery storage—approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023North Northamptonshire9.7

Distance from the average position of the NN16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm175411178
Rooftop solar13211006.2
Wind farm600410
Wind turbine220002
Battery storage11730011

MW in pipeline: pending, approved and under-construction capacity.

How North Northamptonshire decides solar, wind and battery applications

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in North Northamptonshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NN16, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.