Burton Wold Solar Farm - Site A (19.5 MW)

Burton Wold Solar Farm - Site A is a 19.5 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 27 October 2019; the record was last updated on 27 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.5 MWsolar farm
permission expiredstatus in REPD
27 May 2020record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
1 August 2014Application submitted
27 October 2014Planning permission granted
27 October 2019Permission expired

Project details

Technology
solar farm
Capacity
19.5 MW
Status (REPD)
permission expired
Record last updated
27 May 2020
Operator or applicant
First Renewable Developments
Planning authority
North Northamptonshire
Planning application reference
KET/2014/0540
Site area
34.3 ha
Address (REPD)
Wold Road (land south of), Burton Latimer
Council area (by location)
North Northamptonshire
Time to decision
12 weeks
REPD reference
1979

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wold Windfarmwind farm20operational0.1
Burton Wold Wind Farm - Northern Extensionwind farm14.4operational0.7
Burton Wold Wind Farm Southwind farm7.5operational1.3
Burton Wold Wind Farm Extension (Southern)wind farm8.6abandoned1.3
Wold Cottage Solar Farmsolar farm5approved, not built1.4
Latimer Solar Parksolar farm5approved, not built1.4
Windmill Solar Farmsolar farm5permission expired1.4
Burton Wold Solar Farmsolar farm8.4permission expired1.4
Top Lodge Solar Farmsolar farm5permission expired1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.361, -0.6417).