Energy Projects Near You

Burton Wold Wind Farm South (7.5 MW)

Burton Wold Wind Farm South is a 7.5 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 April 2017; the record was last updated on 24 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
24 April 2017record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
18 February 2015Application submitted
27 March 2015Planning permission granted
15 September 2016Construction started
24 April 2017Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
24 April 2017
Operator or applicant
Infinergy/ Muirhall Energy
Planning authority
North Northamptonshire
Planning application reference
KET/2014/0861
Turbines
3
Turbine height
137 m
Address (REPD)
Land at Glendon Farm, Burton Latimer, Kettering
Council area (by location)
North Northamptonshire
Time to decision
5 weeks
REPD reference
5277

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wold Wind Farm Extension (Southern)wind farm8.6abandoned0.6
Burton Wold Wind Farm - Northern Extensionwind farm14.4operational0.9
Latimer Solar Parksolar farm5approved, not built1.2
Burton Wold Windfarmwind farm20operational1.2
Top Lodge Solar Farmsolar farm5permission expired1.3
Windmill Solar Farmsolar farm5permission expired1.3
Burton Wold Solar Farmsolar farm8.4permission expired1.3
Burton Wold Solar Farm - Site Asolar farm19.5permission expired1.3
Wold Cottage Solar Farmsolar farm5approved, not built1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3536, -0.6565).