Energy Projects Near You

Wold Cottage Solar Farm (5 MW)

Wold Cottage Solar Farm is a 5 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 31 July 2015, not yet built; the record was last updated on 27 May 2020. REPD also records that the planning permission expired on 31 July 2020, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
27 May 2020record last updated
North Northamptonshirecouncil area

REPD also records that the planning permission expired on 31 July 2020, so the project may not go ahead in this form.

Planning timeline

DateStage
1 June 2015Application submitted
31 July 2015Planning permission granted
31 July 2020Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
approved, not built
Record last updated
27 May 2020
Operator or applicant
First Renewable Developments
Planning authority
North Northamptonshire
Planning application reference
KET/2015/0446
Site area
8.4 ha
Address (REPD)
Wold Cottage Farm, Wold Road, Burton Latimer, Kettering
Council area (by location)
North Northamptonshire
Time to decision
9 weeks
REPD reference
5269

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wold Solar Farmsolar farm8.4permission expired0.2
Windmill Solar Farmsolar farm5permission expired0.2
Top Lodge Solar Farmsolar farm5permission expired0.2
Latimer Solar Parksolar farm5approved, not built0.2
Bryant Field Solar Parksolar farm5permission expired0.5
Burton Wold Wind Farm - Northern Extensionwind farm14.4operational0.7
Burton Wold Windfarmwind farm20operational1.3
Burton Wold Wind Farm Southwind farm7.5operational1.4
Burton Wold Solar Farm - Site Asolar farm19.5permission expired1.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3655, -0.6607).