Burton Wold Windfarm (20 MW)

Burton Wold Windfarm is a 20 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 April 2006; the record was last updated on 4 December 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWwind farm
operationalstatus in REPD
4 December 2017record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
23 March 2004Application submitted
23 March 2004Planning permission granted
1 December 2005Construction started
1 April 2006Operational

Project details

Technology
wind farm
Capacity
20 MW
Status (REPD)
operational
Record last updated
4 December 2017
Operator or applicant
Gravis Capital Management
Planning authority
North Northamptonshire
Planning application reference
KE/03/0559
Turbines
10
Address (REPD)
Felaw Maltings, Felaw Street, Ipswich
Council area (by location)
North Northamptonshire
Time to decision
0 weeks
REPD reference
4672

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wold Solar Farm - Site Asolar farm19.5permission expired0.1
Burton Wold Wind Farm - Northern Extensionwind farm14.4operational0.6
Burton Wold Wind Farm Southwind farm7.5operational1.2
Burton Wold Wind Farm Extension (Southern)wind farm8.6abandoned1.3
Wold Cottage Solar Farmsolar farm5approved, not built1.3
Latimer Solar Parksolar farm5approved, not built1.3
Top Lodge Solar Farmsolar farm5permission expired1.3
Burton Wold Solar Farmsolar farm8.4permission expired1.3
Windmill Solar Farmsolar farm5permission expired1.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3608, -0.6431).