Burton Wold Wind Farm Extension (Southern) (8.6 MW)

Burton Wold Wind Farm Extension (Southern) is an 8.6 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 18 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.6 MWwind farm
abandonedstatus in REPD
18 November 2016record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
24 August 2011Application submitted
2 April 2012Planning permission granted
2 April 2014Permission expired

Project details

Technology
wind farm
Capacity
8.6 MW
Status (REPD)
abandoned
Record last updated
18 November 2016
Operator or applicant
Infinergy
Planning authority
North Northamptonshire
Planning application reference
KET/2011/0506
Turbines
3
Turbine height
137 m
Address (REPD)
Glendon Farm (land at), Near Burton Latimer,
Council area (by location)
North Northamptonshire
Time to decision
32 weeks
REPD reference
3821

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Burton Wold Wind Farm Southwind farm7.5operational0.6
Burton Wold Wind Farm - Northern Extensionwind farm14.4operational1.3
Burton Wold Windfarmwind farm20operational1.3
Burton Wold Solar Farm - Site Asolar farm19.5permission expired1.3
Latimer Solar Parksolar farm5approved, not built1.7
Top Lodge Solar Farmsolar farm5permission expired1.8
Burton Wold Solar Farmsolar farm8.4permission expired1.8
Windmill Solar Farmsolar farm5permission expired1.8
Wold Cottage Solar Farmsolar farm5approved, not built1.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3502, -0.6502).