Solar, wind and battery projects near Wellingborough (NN9)
39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NN9 (North Northamptonshire): 5 are waiting for a planning decision, 11 approved but not yet running, 13 operational. The largest live scheme is Wood Lodge Farm, Huntingdon Road Solar Farm (50 MW solar farm, application submitted on 12 September 2023, no decision recorded; REPD status may be out of date), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NN9
Projects of 1 MW and more (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Quarry, Ditchford Lane Solar Farmsolar farm | solar farm | 10 | approved, not builtupdated Jun 2026 | Jan 2025 | granted Jun 2026 | Jun 2026 | North Northamptonshire | 3.7 |
| Burton Wold Wind Farm Extension (Southern)wind farm | wind farm | 8.6 | abandonedupdated Nov 2016 | Aug 2011 | granted Apr 2012 | Nov 2016 | North Northamptonshire | 4.2 |
| Burton Wold Solar Farm - Site Asolar farm | solar farm | 19.5 | permission expiredupdated May 2020 | Aug 2014 | granted Oct 2014 | May 2020 | North Northamptonshire | 4.4 |
| Burton Wold Windfarmwind farm | wind farm | 20 | operationalupdated Dec 2017 | Mar 2004 | granted Mar 2004 | Dec 2017 | North Northamptonshire | 4.4 |
| Burton Wold Wind Farm Southwind farm | wind farm | 7.5 | operationalupdated Apr 2017 | Feb 2015 | granted Mar 2015 | Apr 2017 | North Northamptonshire | 4.8 |
| Chelveston Renewable Energy Park Wind Farm (Bedford)wind farm | wind farm | 10 | operationalupdated May 2014 | Mar 2010 | granted Jun 2012 | May 2014 | North Northamptonshire | 4.9 |
| Burton Wold Wind Farm - Northern Extensionwind farm | wind farm | 14.4 | operationalupdated Dec 2015 | Aug 2012 | granted Nov 2012 | Dec 2015 | North Northamptonshire | 5.0 |
| Chelveston Renewable Energy Parkbattery storage | battery storage | 20 | under constructionupdated May 2020 | Apr 2017 | granted May 2018 | May 2020 | North Northamptonshire | 5.0 |
| Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)wind farm | wind farm | 12.5 | operationalupdated May 2014 | Mar 2010 | granted Jun 2012 | May 2014 | North Northamptonshire | 5.4 |
| Chelveston Renewable Energy Park Solar Extensionsolar farm | solar farm | 19.5 | operationalupdated Jun 2015 | Jun 2014 | granted Oct 2014 | Jun 2015 | North Northamptonshire | 5.6 |
| Chelveston Renewable Energy Parksolar farm | solar farm | 21 | permission expiredupdated Jul 2018 | Mar 2015 | granted Jun 2015 | Jul 2018 | North Northamptonshire | 5.7 |
| Latimer Solar Parksolar farm | solar farm | 5 | approved, not built may be out of dateupdated May 2020 | Jun 2015 | granted Aug 2015 | May 2020 | North Northamptonshire | 5.7 |
| Wold Cottage Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated May 2020 | Jun 2015 | granted Jul 2015 | May 2020 | North Northamptonshire | 5.7 |
| Burton Wold Solar Farmsolar farm | solar farm | 8.4 | permission expiredupdated May 2020 | Feb 2015 | granted Apr 2015 | May 2020 | North Northamptonshire | 5.7 |
| Windmill Solar Farmsolar farm | solar farm | 5 | permission expiredupdated May 2020 | Jun 2015 | granted Jul 2015 | May 2020 | North Northamptonshire | 5.7 |
| Top Lodge Solar Farmsolar farm | solar farm | 5 | permission expiredupdated May 2020 | Jun 2015 | granted Jul 2015 | May 2020 | North Northamptonshire | 5.7 |
| Chelveston Airfieldsolar farm | solar farm | 16 | operationalupdated Jun 2014 | Dec 2012 | granted Apr 2013 | Jun 2014 | Bedford | 5.8 |
| Bryant Field Solar Parksolar farm | solar farm | 5 | permission expiredupdated May 2020 | Jun 2015 | granted Jul 2015 | May 2020 | North Northamptonshire | 6.0 |
| Chelveston Airfield - extensionsolar farm | solar farm | 3.5 | operationalupdated Dec 2014 | Mar 2014 | granted Jun 2014 | Dec 2014 | Bedford | 6.2 |
| Little Irchester, Higham Road Solar Farmsolar farm | solar farm | 4.6 | operationalupdated Jul 2018 | Apr 2015 | granted Jul 2015 | Jul 2018 | North Northamptonshire | 6.6 |
| Gooseys Lodge, Wymington Lane Solar Farmsolar farm | solar farm | 10.4 | approved, not builtupdated May 2024 | Dec 2023 | granted May 2024 | May 2024 | Bedford | 8.1 |
| London Road, Irchester Solar Farmsolar farm | solar farm | 26 | operationalupdated Feb 2024 | May 2022 | granted Nov 2022 | Feb 2024 | North Northamptonshire | 8.1 |
| Colpmans Farmsolar farm | solar farm | 5 | operationalupdated Sep 2018 | Jan 2011 | granted May 2011 | Sep 2018 | North Northamptonshire | 8.2 |
| Goosey Lodge Solar Farmsolar farm | solar farm | 10.5 | approved, not built may be out of dateupdated Jun 2023 | Jul 2022 | granted May 2023 | Jun 2023 | Bedford | 8.3 |
| Wellingborough Solar Farmsolar farm | solar farm | 8.5 | operationalupdated Nov 2014 | Jul 2013 | granted Oct 2013 | Nov 2014 | North Northamptonshire | 9.0 |
| Vicarage Farmbattery storage | battery storage | 50 | refusedupdated Jan 2026 | Jul 2025 | refused Dec 2025 | Jan 2026 | North Northamptonshire | 9.1 |
| Glebe Farm Solar Energy Parksolar farm | solar farm | 15 | operationalupdated Apr 2015 | Feb 2013 | granted Jun 2013 | Apr 2015 | Bedford | 9.1 |
| Wood Lodge Farm, Huntingdon Road Solar Farmsolar farm | solar farm | 50 | application submitted may be out of dateupdated Sep 2023 | Sep 2023 | — | Sep 2023 | North Northamptonshire | 9.5 |
| Wood Lodge Farm, Huntingdon Road Solar Farmbattery storage | battery storage | 8.8 | refusedupdated Oct 2024 | Sep 2023 | refused Oct 2024 | Oct 2024 | North Northamptonshire | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Chelveston Road, Higham Ferrersbattery storage | battery storage | 0.2 | application submittedupdated Mar 2026 | Jan 2026 | — | Mar 2026 | North Northamptonshire | 3.0 |
| Northampton Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Nov 2025 | Oct 2025 | — | Nov 2025 | North Northamptonshire | 4.6 |
| Wold Road (land south of) Peak Power Generation Plantbattery storage | battery storage | — | permission expiredupdated May 2020 | Sep 2015 | — | May 2020 | North Northamptonshire | 4.7 |
| Kettering Energy Parksolar farm | solar farm | — | application submittedupdated May 2025 | Mar 2025 | — | May 2025 | North Northamptonshire | 5.7 |
| Kettering Energy Parkbattery storage | battery storage | — | application submittedupdated May 2025 | Mar 2025 | — | May 2025 | North Northamptonshire | 5.7 |
| Claudius Wayrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 | North Northamptonshire | 7.3 |
| Nene Community Centre, Cedar Driverooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Jan 2025 | granted Oct 2025 | Nov 2025 | North Northamptonshire | 7.4 |
| Westwood A D Plant, Bedford Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2026 | Mar 2026 | granted Mar 2026 | Jun 2026 | North Northamptonshire | 8.2 |
| Trinity Centre, Sinclair Drivebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2026 | Oct 2025 | granted Feb 2026 | Apr 2026 | North Northamptonshire | 9.9 |
| Sainsburys Store And Petrol, Northampton Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | North Northamptonshire | 9.9 |
Distance from the average position of the NN9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 21 | 2 | 5 | 8 | 0 | 90.9 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 1.2 |
| Wind farm | 6 | 0 | 0 | 5 | 0 | 0 |
| Battery storage | 8 | 3 | 2 | 0 | 2 | 20.6 |
MW in pipeline: pending, approved and under-construction capacity.
How North Northamptonshire decides solar, wind and battery applications
| Applications | North Northamptonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 11 (16%) | 19% |
| Solar refused | 2 of 44 | 12% |
| Onshore wind refused | 5 of 11 | 45% |
| Battery storage refused | 4 of 13 | 16% |
| Median time from submission to decision | 11.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
All projects in North Northamptonshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NN9, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.