Energy Projects Near You

Gooseys Lodge, Wymington Lane Solar Farm (10.4 MW)

Gooseys Lodge, Wymington Lane Solar Farm is a 10.4 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 2 May 2024, not yet built; the record was last updated on 13 May 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10.4 MWsolar farm
approved, not builtstatus in REPD
13 May 2024record last updated
Bedfordcouncil area

Planning timeline

DateStage
11 December 2023Application submitted
2 May 2024Planning permission granted
2 May 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10.4 MW
Status (REPD)
approved, not built
Record last updated
13 May 2024
Operator or applicant
Wykes Engineering Limited Goosey Lodge
Planning authority
Bedford
Planning application reference
23/02517/MAF
Site area
10.6 ha
Address (REPD)
Gooseys Lodge, Wymington Lane, Wymington, Rushden
Council area (by location)
Bedford
Time to decision
20 weeks
Name in REPD
Gooseys Lodge, Wymington Lane - Solar Farm
REPD reference
15707

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goosey Lodge Solar Farmsolar farm10.5approved, not built0.2
Glebe Farm Solar Energy Parksolar farm15operational1.0
Airfield Farm (Podington)wind farm8.6operational3.2
Odell Glebe Solar Farmsolar farm16.8operational3.4
Chelveston Renewable Energy Parksolar farm21permission expired5.3
Land at Wood Roadsolar farm5refused5.6
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)wind farm12.5operational5.6
Quarry, Ditchford Lane Solar Farmsolar farm10approved, not built5.6
London Road, Irchester Solar Farmsolar farm26operational5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.262, -0.588).