Glebe Farm Solar Energy Park (15 MW)

Glebe Farm Solar Energy Park is a 15 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 15 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
operationalstatus in REPD
15 April 2015record last updated
Bedfordcouncil area

Planning timeline

DateStage
5 February 2013Application submitted
3 June 2013Planning permission granted
24 November 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
15 April 2015
Operator or applicant
Vento Ludens
Planning authority
Bedford
Planning application reference
13/00218/MAF
Address (REPD)
Land To The North East Glebe Farm Forty Foot Lane Souldrop
Council area (by location)
Bedford
Time to decision
17 weeks
REPD reference
2352

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Goosey Lodge Solar Farmsolar farm10.5approved, not built0.9
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built1.0
Airfield Farm (Podington)wind farm8.6operational2.3
Odell Glebe Solar Farmsolar farm16.8operational2.4
Land at Wood Roadsolar farm5refused4.6
Nun Wood (Bedford)wind farm18refused on appeal5.9
Nun Wood (Milton Keynes)wind farm9refused on appeal6.0
Chelveston Renewable Energy Parksolar farm21permission expired6.2
Nun Wood (Wellingborough)wind farm9refused on appeal6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2526, -0.5893).