London Road, Irchester Solar Farm (26 MW)

London Road, Irchester Solar Farm is a 26 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational; the record was last updated on 13 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

26 MWsolar farm
operationalstatus in REPD
13 February 2024record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
26 May 2022Application submitted
8 November 2022Planning permission granted
1 April 2023Construction started

Project details

Technology
solar farm
Capacity
26 MW
Status (REPD)
operational
Record last updated
13 February 2024
Operator or applicant
Atrato Onsite Energy
Planning authority
North Northamptonshire
Planning application reference
NW/22/00353/FUL
Site area
65.2 ha
Address (REPD)
Land To The South Of B570, Gipsy Lane, Irchester, Wellingborough,
Council area (by location)
North Northamptonshire
Time to decision
24 weeks
Name in REPD
London Road, Irchester - Solar Farm
REPD reference
11423

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Vicarage Farmbattery storage50refused1.0
Wellingborough Solar Farmsolar farm8.5operational1.6
Quarry, Ditchford Lane Solar Farmsolar farm10approved, not built4.5
Grendon Lakes, Grendonbattery storage50approved, not built5.3
Grendon Storagebattery storage49.9permission expired5.3
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built5.9
Grendon Road, Earls Bartonbattery storage99.9approved, not built6.0
Goosey Lodge Solar Farmsolar farm10.5approved, not built6.0
Glebe Farm Solar Energy Parksolar farm15operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2788, -0.6707).