Burton Wold Wind Farm - Northern Extension (14.4 MW)
Burton Wold Wind Farm - Northern Extension is a 14.4 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2014; the record was last updated on 21 December 2015.
14.4 MWwind farm
operationalstatus in REPD
21 December 2015record last updated
North Northamptonshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 29 August 2012 | Application submitted |
| 9 November 2012 | Planning permission granted |
| 21 October 2013 | Construction started |
| 1 August 2014 | Operational |
Project details
- Technology
- wind farm
- Capacity
- 14.4 MW
- Status (REPD)
- operational
- Record last updated
- 21 December 2015
- Operator or applicant
- John Laing Environmental Assets Group
- Planning authority
- North Northamptonshire
- Planning application reference
- KET/2012/0556
- Turbines
- 9
- Address (REPD)
- Burton Wold Wind Farm, Wold Road, Burton Latimer
- Council area (by location)
- North Northamptonshire
- Time to decision
- 10 weeks
- REPD reference
- 4210
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Burton Wold Wind Farm Extension KET/2007/1033 | 16.1 | 23 November 2007 | replaced by a revised application |
Who decides
| Applications | North Northamptonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 68 | 10,236 |
| Refused | 11 (16%) | 19% |
| Solar refused | 2 of 44 | 12% |
| Onshore wind refused | 5 of 11 | 45% |
| Battery storage refused | 4 of 13 | 16% |
| Median time from submission to decision | 11.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Burton Wold Windfarm | wind farm | 20 | operational | 0.6 |
| Burton Wold Solar Farm - Site A | solar farm | 19.5 | permission expired | 0.7 |
| Latimer Solar Park | solar farm | 5 | approved, not built | 0.7 |
| Wold Cottage Solar Farm | solar farm | 5 | approved, not built | 0.7 |
| Burton Wold Solar Farm | solar farm | 8.4 | permission expired | 0.8 |
| Windmill Solar Farm | solar farm | 5 | permission expired | 0.8 |
| Top Lodge Solar Farm | solar farm | 5 | permission expired | 0.8 |
| Burton Wold Wind Farm South | wind farm | 7.5 | operational | 0.9 |
| Bryant Field Solar Park | solar farm | 5 | permission expired | 1.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3616, -0.6518).