Chelveston Renewable Energy Park (20 MW)

Chelveston Renewable Energy Park is a 20 MW battery storage project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 July 2019; the record was last updated on 27 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
under constructionstatus in REPD
27 May 2020record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
20 April 2017Application submitted
10 May 2018Planning permission granted
1 July 2019Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
under construction
Record last updated
27 May 2020
Operator or applicant
Federal Estates
Planning authority
North Northamptonshire
Planning application reference
17/00784/FUL
Address (REPD)
Chelveston Renewable Energy Pa, The Airfield, Chelveston, Wellingborough,
Council area (by location)
North Northamptonshire
Time to decision
55 weeks
REPD reference
6941

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chelveston Renewable Energy Park Wind Farm (Bedford)wind farm10operational0.6
Chelveston Renewable Energy Park Solar Extensionsolar farm19.5operational0.8
Chelveston Airfieldsolar farm16operational1.0
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)wind farm12.5operational1.1
Chelveston Renewable Energy Parksolar farm21permission expired1.5
Quarry, Ditchford Lane Solar Farmsolar farm10approved, not built6.4
Gooseys Lodge, Wymington Lane Solar Farmsolar farm10.4approved, not built6.7
Goosey Lodge Solar Farmsolar farm10.5approved, not built6.8
Glebe Farm Solar Energy Parksolar farm15operational7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3107, -0.5309).