Energy Projects Near You

Barnwell Manor Wind Farm (10 MW)

Barnwell Manor Wind Farm is a 10 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 February 2014; the record was last updated on 3 March 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWwind farm
refused on appealstatus in REPD
3 March 2014record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
9 February 2010Application submitted
24 January 2011Refused by the planning authority
18 February 2014Appeal refused

Project details

Technology
wind farm
Capacity
10 MW
Status (REPD)
refused on appeal
Record last updated
3 March 2014
Operator or applicant
Barnwell Manor Wind Energy Ltd
Planning authority
North Northamptonshire
Planning application reference
10/00068/FUL
Appeal reference
11/00011/REF
Turbines
4
Address (REPD)
Area North Of Catshead Woods, Brigstock Road, Sudborough, Northamptonshire
Council area (by location)
North Northamptonshire
Time to decision
50 weeks
REPD reference
3825

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Photovoltaic Panelssolar farm39.3application submitted2.2
Colpmans Farmsolar farm5operational4.3
Brigstock Solar Farmsolar farm49.9approved, not built4.5
Grafton Underwoodsolar farm38approved, not built5.2
Oakley Bush Solar Farmbattery storage10application submitted8.6
Solar PV Panelssolar farm39application submitted8.6
Foxholes Farm, Roman Roadsolar farm49.9application submitted8.9
Wood Lodge Farm, Huntingdon Road Solar Farmsolar farm50application submitted9.0
Bryant Field Solar Parksolar farm5permission expired9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4426, -0.5792).